Estimates for construction of recommendations were developed to complement the Plan. They were developed by identifying pay items and establishing rough per-mile quantities. Unit costs are based on 2013 dollars and were assigned based on historical cost data from the NCDOT, the UNC-Chapel Hill Highway Safety Research Center – Costs for Pedestrian and Bicyclist Infrastructure Improvements Report, the Town and other sources such as RS Means, a leading source of construction cost information. The costs shown only reflect cost associated with construction of the particular bicycle facility indicated and do not reflect other costs that may be associated with a larger project. The costs are intended to be general and used for long-range planning purposes. A 10-30% contingency is applied to the cost for each item based on the scale of the project. For example:
- 10% contingency applied to signed bicycle routes and shared lane marking projects as they are relatively straightforward.
- 20% contingency applied to projects which add bicycle facilities through such actions as lane diets, road diets or projects which fix existing infrastructure.
- 30% contingency is applied to projects which require substantial construction efforts such as widening roadways, construction of greenways or sidepaths or the installation of lighting.
- No contingency is applied to bridge projects as these estimates are based on historical pricing for bridges on a square foot basis.
The construction estimates do not include costs for planning, surveying, engineering design, right-of-way acquisition, complete edge to edge roadway reconstruction, addition of closed drainage systems, mobilization or future maintenance. Construction costs will vary based on the ultimate project scope (i.e. combination with other projects) and economic conditions at the time of construction.
The costs for intersection study, bicycle channels and ramps are approximations to aid in setting budgets. The materials likely to be utilized and the method of construction for bicycle channels and ramps varies greatly from location to location.
The following tables provide the assumptions utilized to calculate the probable construction cost for each potential bicycle network project. The tables identify the facility type with the corresponding implementation action. An example is:
Facility Type (Action) –> Sharrows, SH (Add Markings, AM)
Cost are calculated on a per mile basis and applied to the actual project mileage on the UNC_CH Summary Table. The Item Costs are also shown on the individual Project Descriptions in Appendix D. Exceptions to this approach include the following which are listed under the “Other Projects” category:
- William Blythe Drive because it only recommends the addition of bicycle lanes through existing lane narrowing.
- Bicycle stair channel and bicycle ramp retrofits which are shown on the short term map and described in Chapter 3.
- Intersection study recommendations which are shown on the short term map and described in Chapter 3.
- Development of a signed route system throughout campus as described in Chapter 3 and shown on primary and secondary bicycle route map shown in Chapter 3.
| Location/Description | Recommendation | Action | Length (Mile) | Cost/Mile | Item Cost |
|---|---|---|---|---|---|
| 1. Country Club Road | |||||
| Short Term | Climbing Lane | Lane Diet, LD | 0.4 | $132,300 | $52,920 |
| LT Option 1 | Bicycle Lanes | Lane Diet, LD + Parking Removal | 0.4 | $156,700 | $62,680 |
| LT Option 2 | Bicycle Lanes | Widen Roadway Closed, WRC | 0.4 | $3,990,100 | $1,596,040 |
| LT Option 3 | Shared Use Path | Sidepath, Reconstruct Sidewalk | 0.4 | $1,377,100 | $550,840 |
| 2. East Cameron Avenue | |||||
| Short Term | None | N/A | N/A | N/A | N/A |
| LT Option 1 | Shared Lane Markings | Add Markings, AM | 0.4 | $19,300 | $7,720 |
| 3. Hibbard Drive | |||||
| Short Term | Climbing Lane | Lane Diet, LD | 0.3 | $132,300 | $39,690 |
| LT Option 1 | Bicycle Lanes | Widen Roadway Closed, WRC | 0.3 | $3,990,100 | $1,197,030 |
| 4. Kenan-Flagler Connector | |||||
| Short Term | None | N/A | N/A | N/A | N/A |
| LT Option 1 | Bridge | Two 300 foot bridges | 600 | $17,500 | $10,500,000 |
| 5. Kenan Stadium East Path Connector | |||||
| Short Term | Reconstruct Intersection | Reconstruct Intersection | 1 | $50,000 | $50,000 |
| LT Option 1 | Shared Use Path | Widen Roadway Closed, WRC | 0.15 | $3,990,100 | $598,515 |
| 6. Kenan Stadium West Path Connector | |||||
| Short Term | Shared Lane Markings | Add Markings, AM | 0.2 | $19,300 | $3,860 |
| Short Term | Bicycle Ramp | Bicycle Ramp | 1 | $10,000 | $10,000 |
| LT Option 1 | Shared Use Path | Greenway, Construct | 0.2 | $576,700 | $115,340 |
| 7. Manning Drive | |||||
| Short Term | Shared Lane Markings | Add Markings, AM | 0.6 | $19,300 | $11,580 |
| Short Term | Climbing Lane | Lane Diet, LD | 0.6 | $132,300 | $79,380 |
| LT Option 1 | Shared Use Path 1 side | Sidepath, Reconstruct Sidewalk | 0.6 | $1,377,100 | $826,260 |
| LT Option 2 | Shared Use Path Section | Sidepath, Reconstruct Sidewalk | 0.15 | $1,377,100 | $206,565 |
| 8. Mason Farm Road | |||||
| Short Term | Shared Lane Markings | Add Markings, AM | 0.8 | $19,300 | $15,440 |
| LT Option 1 | 2-Way Cycle Track | Widen Roadway Closed, WRC | 0.8 | $1,909,100 | $1,527,280 |
| LT Option 2 | Bicycle Lanes | Widen Roadway Closed, WRC | 0.8 | $2,061,000 | $1,648,800 |
| 9. McCauley Street | |||||
| Short Term | Shared Lane Markings | Add Markings, AM | 0.1 | $19,300 | $1,930 |
| LT Option 1 | 2-Way Cycle Track | Widen Roadway Closed, WRC | 0.1 | $1,909,100 | $190,910 |
| LT Option 2 | Bicycle Lanes | Widen Roadway Closed, WRC | 0.1 | $3,990,100 | $399,010 |
| 10. Paul Hardin Drive | |||||
| Short Term | Shared Lane Markings | Add Markings, AM | 0.15 | $19,300 | $2,895 |
| LT Option 1 | Shared Use Path | Sidepath, Reconstruct Sidewalk | 0.15 | $1,377,100 | $206,565 |
| LT Option 2 | Bicycle Lanes | Widen Roadway Closed, WRC | 0.15 | $3,990,100 | $598,515 |
| 11. Skipper Bowles Drive | |||||
| Short Term | Shared Lane Markings | Add Markings, AM | 0.5 | $19,300 | $9,650 |
| LT Option 1 | Shared Use Path | Reconstruct Sidewalk | 0.5 | $1,377,100 | $688,550 |
| 12. South Columbia Street | |||||
| ST Option 1 | Shared Lane Markings | Add Markings, AM | 0.3 | $19,300 | $5,790 |
| ST Option 2 | Bicycle Lane | Lane Diet, LD | 0.3 | $156,700 | $47,010 |
| LT Option 1(a) | 2-Way Cycle Track | 2-Way Cycle Track | 0.3 | $1,909,100 | $572,730 |
| LT Option 1(b) | 2-Way Cycle Track | Widen Roadway Closed, WRC | 0.3 | $3,990,100 | $1,197,030 |
| LT Option 2 | Shared Use Path | Sidepath, Reconstruct Sidewalk | 0.3 | $1,377,100 | $413,130 |
| 13. Ridge Road | |||||
| Short Term A1, B1 | Climbing Lane | Lane Diet, LD | 0.3 | $132,300 | $39,690 |
| Short Term A1, B2 | Shared Lane Markings | Add Markings, AM | 0.4 | $19,300 | $7,720 |
| LT Option A1 | Bicycle Lanes | Road Diet, RD | 0.2 | $164,000 | $32,800 |
| LT Option A2 | Bicycle Lanes | Widen Roadway Closed, WRC | 0.2 | $3,990,100 | $798,020 |
| LT Option A3 | Shared Use Path | Sidepath, Reconstruct Sidewalk | 0.2 | $1,377,100 | $275,420 |
| LT Option B1 | Bicycle Lanes | Widen Roadway Closed, WRC | 0.1 | $3,990,100 | $399,010 |
| LT Option B2 | Shared Use Path | Sidepath, Reconstruct Sidewalk | 0.1 | $1,377,100 | $137,710 |
| LT Option C1 | Climbing Lane | Widen Roadway Closed, WRC | 0.4 | $2,006,400 | $802,560 |
| LT Option C2 | Bicycle Lanes | Widen Roadway Closed, WRC | 0.4 | $3,990,100 | $1,560,040 |
| LT Option C3 | Shared Use Path | Sidepath, Reconstruct Sidewalk | 0.4 | $1,377,100 | $550,840 |
| 14. Stadium Drive | |||||
| ST Option 1 | Climbing Lane | Lane Diet, LD | 0.4 | $132,300 | $52,920 |
| ST Option 2 | Bicycle Lanes | Road Diet | 0.4 | $164,000 | $65,600 |
| LT Option 2 | 2-Way Cycle Track | 2-Way Cycle Track | 0.4 | $1,909,100 | $763,640 |
| LT Option 3 | Shared Use Path | Sidepath, Reconstruct Sidewalk | 0.4 | $1,377,100 | $550,840 |
| 15. Raleigh Street | |||||
| Short Term | Shared Lane Markings | Add Markings, AM | 0.4 | $19,300 | $7,720 |
| Long Term | None | N/A | N/A | N/A | N/A |
| 16. South Road | |||||
| Short Term | Shared Lane Markings | Add Markings, AM | 0.65 | $19,300 | $12,545 |
| LT Option 1A | Bicycle Lanes | Road Diet | 0.35 | $164,000 | $57,400 |
| LT Option 1B | Bicycle Lanes | Add Markings | 0.3 | $69,900 | $20,970 |
| LT Option 2A | Raised Bicycle Lanes | Sidepath, Reconstruct Sidewalk | 0.35 | $1,377,100 | $481,985 |
| LT Option 2B | Raised Bicycle Lanes | Sidepath, Reconstruct Sidewalk | 0.3 | $1,377,100 | $413,130 |
| LT Option 3 | One-Way Cycle Tracks (A) | One-Way Cycle Track | 0.35 | $2,446,900 | $856,415 |
| Other Projects | |||||
| William Blythe Drive | Bicycle Lanes | Add Markings, AM | 0.3 | $69,900 | $20,970 |
| See short-term map | Bicycle Stair Channel | Retrofit | 6 | $5,000 | $30,000 |
| See short-term map | Bicycle Ramps | Retrofit | 3 | $5,000 | $15,000 |
| See short-term map | Intersection Study | Study of 25 intersections | 1 | $50,000 | $50,000 |
| See route map | Signed Routes | Add Signs | 15.0 | $6,000 | $90,000 |
Facility Base 2013 Costs (Per Mile)
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of road |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Maintenance of Traffic (Fixed) | LS | 1.00 | $500.00 | $500 | |
| Subtotal | $5,420 | ||||
| 10% Contingency | $542 |
Total Estimated Cost: $6,000 –> $1.14 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Thermoplastic Pavement Marking Symbol | EA | 40 | $275.00 | $11,000 | 1 Symbol every 250′, each side of road |
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of road |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Maintenance of Traffic (10%) | LS | 1.00 | $1,592.00 | $1,592 | |
| Subtotal | $17,512 | ||||
| 10% Contingency | $1,751 |
Total Estimated Cost: $19,300 –> $3.66 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Thermoplastic Pavement Marking Lines (4″ to 6″) | LF | 21,120 | $1.75 | $36,960 | 4 solid lines entire length |
| Thermoplastic Pavement Marking Symbol | EA | 40 | $275.00 | $11,000 | 1 Symbol every 250′, each side of road |
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of road |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Maintenance of Traffic (10%) | LS | 1.00 | $5,288.00 | $5,288 | |
| Subtotal | $58,168 | ||||
| 20% Contingency | $11,634 |
Total Estimated Cost: $69,900 –> $13.24 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Thermoplastic Pavement Marking Lines (4″ to 6″) | LF | 31,680 | $1.75 | $55,440 | 6 solid lines entire length |
| Thermoplastic Pavement Marking Symbol | EA | 40 | $275.00 | $11,000 | 1 Symbol every 250′, each side of road |
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of road |
| Eradication | LF | 21,120 | $2.24 | $47,309 | Eradicate 4 solid lane lines |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Maintenance of Traffic (10%) | LS | 1.00 | $11,867.00 | $11,867 | |
| Subtotal | $130,536 | ||||
| 20% Contingency | $26,107 |
Total Estimated Cost: $156,700 –> $29.68 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Thermoplastic Pavement Marking Lines (4″ to 6″) | LF | 31,680 | $1.75 | $55,440 | 6 solid lines entire length (4-3 road diet) |
| Thermoplastic Pavement Marking Bike Lane Symbol | EA | 40 | $275.00 | $11,000 | 1 Bike Symbol every 250′, each side of road |
| Thermoplastic Pavement Marking Arrow Symbol | EA | 40 | $275.00 | $5,500 | 1 Turn Arrow every 500′, each side of road |
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of road |
| Eradication | LF | 21,120 | $2.24 | $47,309 | Eradicate 4 solid lane lines |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Maintenance of Traffic (10%) | LS | 1.00 | $12,417.00 | $12,417 | |
| Subtotal | $136,586 | ||||
| 20% Contingency | $27,317 |
Total Estimated Cost: $164,000 –> $31.06 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Earthwork, Excavation, Grading | CY | 21,902 | $17.00 | $372,338 | 7′ width and 2′ depth, each side of road |
| Aggregate Base Course for Pavement | CY | 2,738 | $56.00 | $153,316 | 7′ width and 1′ depth, each side of road |
| Milling | SY | 12,907 | $7.00 | $90,347 | 22′ width |
| Asphalt Base Course | TON | 2,779 | $67.00 | $186,189 | 14′ width and 0.5′ depth, 13.3 CF in a TON |
| Asphalt Surface Course | TON | 1,786 | $67.00 | $119,693 | 36′ width and 0.125′ depth, 13.3 CF in a TON |
| Thermoplastic Pavement Marking Lines (4″ to 6″) | LF | 21,120 | $1.75 | $36,960 | 4 solid lines entire length |
| Thermoplastic Pavement Marking Symbol | EA | 40 | $275.00 | $11,000 | 1 Symbol every 250′, each side of road (bike lane) |
| Crosswalk | EA | 4 | $1,000.00 | $4,000 | 4 Crosswalks per mile, 36′ x 10′, High Visibility |
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of road |
| Retaining Wall (up to 6′ height) | LF | 528 | $500.00 | $264,000 | 10% of length |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Landscaping (5%) | LS | 1.00 | $48,938.00 | $48.938 | |
| Drainage and E&S (10%) | LS | 1.00 | $97,876.00 | $97,876 | |
| Maintenance of Traffic (10%) | LS | 1.00 | $97,876.00 | $97,876 | |
| Utility Adjustments (10%) | LS | 1.00 | $97,876.00 | $97,876 | |
| Subtotal | $1,585,329 | ||||
| 30% Contingency | $475,599 |
Total Estimated Cost: $2,061,000 –> $390.34 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Earthwork, Fill, Excavation, Grading | CY | 31,289 | $17.00 | $531,911 | 20′ width up to 8′ depth |
| Aggregate Base Course for Pavement | CY | 2,738 | $56.00 | $153,316 | 7′ width and 1′ depth, each side of road |
| Milling | SY | 12,907 | $7.00 | $90,347 | 22′ width |
| Asphalt Base Course | TON | 2,779 | $67.00 | $186,189 | 14′ width and 0.5′ depth, 13.3 CF in a TON |
| Asphalt Surface Course | TON | 1,786 | $67.00 | $119,693 | 36′ width and 0.125′ depth, 13.3 CF in a TON |
| Remove Curb and Gutter | LF | 5,280 | $7.00 | $36,960 | both sides |
| Remove 4′ sidewalk | SY | 4,693 | $4.00 | $18,773 | both sides |
| Curb and Gutter | LF | 10,560 | $20.00 | $211,200 | both sides |
| Construct 5′ sidewalk | SY | 5,867 | $58.00 | $340,267 | both sides |
| Thermoplastic Pavement Marking Lines (4″ to 6″) | LF | 21,120 | $1.75 | $36,960 | 4 solid lines entire length |
| Thermoplastic Pavement Marking Symbol | EA | 40 | $275.00 | $11,000 | 1 Symbol every 250′, each side of road (bike lane) |
| Crosswalk | EA | 4 | $1,000.00 | $4,000 | 4 Crosswalks per mile, 36′ x 10′, High Visibility |
| Retaining Wall (up to 6′ height) | LF | 1,056 | $500.00 | $528,000 | 10% of length |
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of road |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Landscaping (5%) | LS | 1.00 | $113,677.00 | $113,677 | |
| Drainage and E&S (10%) | LS | 1.00 | $227,354.00 | $227,354 | |
| Maintenance of Traffic (10%) | LS | 1.00 | $227,354.00 | $227,354 | |
| Utility Adjustments (10%) | LS | 1.00 | $227,354.00 | $227,354 | |
| Subtotal | $3,069,275 | ||||
| 30% Contingency | $920,783 |
Total Estimated Cost: $3,990,100 –> $755.70 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Thermoplastic Pavement Marking Lines (4″ to 6″) | LF | 5,280 | $1.75 | $9,240 | 1 solid line entire length |
| Thermoplastic Pavement Marking Symbol | EA | 40 | $275.00 | $11,000 | 1 Symbol every 250′, each side of road |
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of road |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Maintenance of Traffic (10%) | LS | 1.00 | $2,516.00 | 2,516 | |
| Subtotal | $27,676 | ||||
| 20% Contingency | $5,535 |
Total Estimated Cost: $33,300 –> $6.31 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Thermoplastic Pavement Marking Lines (4″ to 6″) | LF | 21,120 | $1.75 | $36,960 | 4 solid lines entire length |
| Thermoplastic Pavement Marking Symbol | EA | 40 | $275.00 | $11,000 | 1 Symbol every 250′, each side of road (bike lane) |
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of road |
| Eradication | LF | 21,120 | $2.24 | $43,309 | 4 solid lines entire length |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Maintenance of Traffic (10%) | LS | 1.00 | $10,019.00 | $10,019 | |
| Subtotal | $110,208 | ||||
| 20% Contingency | $22,042 |
Total Estimated Cost: $132,300 –> $25.06 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Earthwork, Fill, Excavation, Grading | CY | 10,951 | $17.00 | $186,169 | 10′ width up to 8′ depth, one side of road |
| Aggregate Base Course | CY | 1,369 | $25.00 | $34,222 | 7′ width and 1′ depth, one side of road |
| Milling | SY | 12,907 | $7.00 | $90,347 | 22′ width |
| Asphalt Base Course | TON | 1,389 | $67.00 | $93,095 | 14′ width and 0.5′ depth, 13.3 CF in a TON |
| Asphalt Surface Course | TON | 1,439 | $67.00 | $96,420 | 29′ width and 0.125′ depth, 13.3 CF in a TON |
| Curb and Gutter | LF | 0 | $20.00 | $0 | none provided |
| Construct 5′ sidewalk | SY | 0 | $58.00 | $0 | none provided |
| Thermoplastic Pavement Marking Lines (4″ to 6″) | LF | 21,120 | $1.75 | $36,960 | 4 solid lines entire length |
| Thermoplastic Pavement Marking Symbol | EA | 40 | $275.00 | $11,000 | 1 Symbol every 250′, each side of road (bike lane) |
| Crosswalk | EA | 4 | $1,000.00 | $4,000 | 4 Crosswalks per mile, 36′ x 10′, High Visibility |
| Retaining Wall (up to 6′ height) | LF | 528 | $500.00 | $264,000 | 10% of length |
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of road |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Landscaping (5%) | LS | 1.00 | $41,057.00 | $41,057 | |
| Drainage and E&S (10%) | LS | 1.00 | $82,113.00 | $82,113 | |
| Maintenance of Traffic (10%) | LS | 1.00 | $82,113.00 | $82,113 | |
| Utility Adjustments (10%) | LS | 1.00 | $82,113.00 | $82,113 | |
| Subtotal | $1,108,528 | ||||
| 30% Contingency | $332,558 |
Total Estimated Cost: $1,441,100 –> $272.94 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Earthwork, Fill, Excavation, Grading | CY | 10,951 | $17.00 | $186,169 | 10′ width up to 8′ depth, one side of road |
| Aggregate Base Course | CY | 1,369 | $25.00 | $34,222 | 7′ width and 1′ depth, one side of road |
| Milling | SY | 12,907 | $7.00 | $90,347 | 22′ width |
| Asphalt Base Course | TON | 1,389 | $67.00 | $93,095 | 14′ width and 0.5′ depth, 13.3 CF in a TON |
| Asphalt Surface Course | TON | 1,439 | $67.00 | $96,420 | 29′ width and 0.125′ depth, 13.3 CF in a TON |
| Remove Curb and Gutter | LF | 5,280 | $7.00 | $36,960 | one side |
| Remove 4′ sidewalk | SY | 2,347 | $4.00 | $9,387 | one side |
| Curb and Gutter | LF | 5,280 | $20.00 | $105,600 | one side |
| Construct 5′ sidewalk | SY | 2,933 | $58.00 | $170,133 | one side |
| Thermoplastic Pavement Marking Lines (4″ to 6″) | LF | 21,120 | $1.75 | $36,960 | 4 solid lines entire length |
| Thermoplastic Pavement Marking Symbol | EA | 40 | $275.00 | $11,000 | 1 Symbol every 250′, each side of road (bike lane) |
| Crosswalk | EA | 4 | $1,000.00 | $4,000 | 4 Crosswalks per mile, 36′ x 10′, High Visibility |
| Retaining Wall (up to 6′ height) | LF | 528 | $500.00 | $264,000 | 10% of length |
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of road |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Landscaping (5%) | LS | 1.00 | $57,161.00 | $57,161 | |
| Drainage and E&S (10%) | LS | 1.00 | $114,321.00 | $114,321 | |
| Maintenance of Traffic (10%) | LS | 1.00 | $114,321.00 | $114,321 | |
| Utility Adjustments (10%) | LS | 1.00 | $114,321.00 | $114,321 | |
| Subtotal | $1,543,336 | ||||
| 30% Contingency | $463,001 |
Total Estimated Cost: $2,006,400 –> $380.00 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Thermoplastic Pavement Marking Lines (4″ to 6″) | LF | 31,680 | $1.75 | $55,440 | 6 solid lines entire length |
| Thermoplastic Pavement Marking Symbol | EA | 40 | $275.00 | $11,000 | 1 Symbol every 250′, each side of road (bike lane) |
| Crosswalk | EA | 4 | $1,000.00 | $4,000 | 4 Crosswalks per mile, 36′ x 10′, High Visibility |
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of road |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Maintenance of Traffic (10%) | LS | 1.00 | $7,536.00 | $7,536 | |
| Subtotal | $82,896 | ||||
| 20% Contingency | $16,579 |
Total Estimated Cost: $99,500 –> $18.84 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Thermoplastic Pavement Marking Lines (4″ to 6″) | LF | 31,680 | $1.75 | $55,440 | 6 solid lines entire length |
| Thermoplastic Pavement Marking Symbol | EA | 40 | $275.00 | $11,000 | 1 Symbol every 250′, each side of road (bike lane) |
| Crosswalk | EA | 4 | $1,000.00 | $4,000 | 4 Crosswalks per mile, 36′ x 10′, High Visibility |
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of road |
| Eradication | LF | 21,120 | $2.24 | $47,309 | 4 solid lines entire length |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Maintenance of Traffic (10%) | LS | 1.00 | $12,267.00 | $12,267 | |
| Subtotal | $134,936 | ||||
| 20% Contingency | $26,987 |
Total Estimated Cost: $162,000 –> $30.68 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Repair Concrete Sidewalk (4″ Thickness) | SY | 1,760 | $58.00 | $102,080 | Assume 25% of existing sidewalk, both sides |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Landscaping (5%) | LS | 1.00 | $5,104.00 | $5,104 | |
| Drainage and E&S (5%) | LS | 1.00 | $5,104.00 | $5,104 | |
| Maintenance of Traffic (10%) | LS | 1.00 | $10,208.00 | $10,208 | |
| Utility Adjustments (5%) | LS | 1.00 | $5,104.00 | $5,104 | |
| Subtotal | $127,600 | ||||
| 30% Contingency | $38,280 |
Total Estimated Cost: $165,900 –> $31.42 Per Foot, $82,950 –> Per Side
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Earthwork, Fill, Excavation, Grading | CY | 3,129 | $17.00 | $53,191 | 4′ width up to 2′ depth, two sides |
| Aggregate Base Course | CY | 1,564 | $25.00 | $39,111 | 4′ width and 1′ depth, both sides |
| Widen Concrete Sidewalk (4″ Thickness) | SY | 4,693 | $58.00 | $272,213 | Assume 4′, both sides |
| Repair Concrete Sidewalk (4″ Thickness) | SY | 1,760 | $58.00 | $102,080 | Assume 25% of existing sidewalk, both sides |
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of road |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Landscaping (5%) | LS | 1.00 | $23,576.00 | $23,576 | |
| Drainage and E&S (5%) | LS | 1.00 | $23,576.00 | $23,576 | |
| Maintenance of Traffic (10%) | LS | 1.00 | $47,152.00 | $47,152 | |
| Utility Adjustments (5%) | LS | 1.00 | $23,576.00 | $23,576 | |
| Subtotal | $589,396 | ||||
| 30% Contingency | $176,819 |
Total Estimated Cost: $766,300 –> $145.13 Per Foot, $383,150 –> Per Side
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Earthwork, Excavation, Grading, Fill | CY | 8,800 | $17.00 | $149,600 | 15′ width and 3′ depth |
| Aggregate Base Course | CY | 1,956 | $25.00 | $48,889 | 10′ width and 1′ depth |
| Asphalt Surface Course | TON | 496 | $67.00 | $33,248 | 10′ width and 0.125′ depth, 13.3 CF in a TON |
| Asphalt Base Course | TON | 1,985 | $67.00 | $132,992 | 10′ width and 0.5′ depth, 13.3 CF in a TON |
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of greenway |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Landscaping (5%) | LS | 1.00 | $18,482.00 | $18,482 | |
| Drainage and E&S (10%) | LS | 1.00 | $36,965.00 | $36,965 | |
| Maintenance of Traffic (5%) | LS | 1.00 | $18,482.00 | $18,482 | |
| Utility Adjustments (10%) | LS | 1.00 | $36,965.00 | $36,965 | |
| Subtotal | $480,543 | ||||
| 30% Contingency | $96,109 |
Total Estimated Cost: $576,700 –> $109.22 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Earthwork, Excavation, Grading, Fill | CY | 1,173 | $17.00 | $19,947 | 30%, 10′ width and 2′ depth |
| Aggregate Base Course | CY | 587 | $25.00 | $14,667 | 30%, 10′ width and 1′ depth |
| Asphalt Surface Course | TON | 496 | $67.00 | $33,248 | 100%, 10′ width and 0.125′ depth, 13.3 CF in a TON |
| Asphalt Base Course | TON | 595 | $67.00 | $39,898 | 30%, 10′ width and 0.5′ depth, 13.3 CF in a TON |
| Milling | SY | 4,107 | $7.00 | $28,747 | assume 70% requires milling at 10′ width |
| Remove existing 10′ asphalt path | SY | 1,760 | $4.00 | $7,040 | assume 30% requires removal at 10′ width |
| Remove 4′ sidewalk | SY | 4,693 | $4.00 | $18,773 | both sides |
| Thermoplastic Pavement Marking Symbol | EA | 40 | $275.00 | $11,000 | 1 Symbol every 250′ (bike lanes) |
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of road |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Landscaping (5%) | LS | 1.00 | $7,973.00 | $7,973 | |
| Drainage and E&S (10%) | LS | 1.00 | $15,947.00 | $15,947 | |
| Maintenance of Traffic (5%) | LS | 1.00 | $7,973.00 | $7,973 | |
| Utility Adjustments (5%) | LS | 1.00 | $7,973.00 | $7,973 | |
| Subtotal | $199,332 | ||||
| 30% Contingency | $59,800 |
Total Estimated Cost: $259,200 –> $49.09 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Earthwork, Excavation, Grading, Fill | CY | 7,822 | $17.00 | $132,978 | 20′ disturbance one side and 2′ depth |
| Aggregate Base Course | CY | 1,956 | $25.00 | $48,889 | 10′ width and 1′ depth |
| Asphalt Surface Course | TON | 496 | $67.00 | $33,248 | 10′ width and 0.125′ depth, 13.3 CF in a TON |
| Asphalt Base Course | TON | 1,985 | $67.00 | $132,992 | 10′ width and 0.5′ depth, 13.3 CF in a TON |
| Remove Curb and Gutter | LF | 5,280 | $7.00 | $36,960 | both sides |
| Remove 6′ sidewalk | SY | 3,520 | $4.00 | $14,080 | both sides |
| Curb and Gutter | LF | 5,280 | $20.00 | $105,600 | both sides |
| Thermoplastic Pavement Marking Symbol | EA | 40 | $275.00 | $11,000 | 1 Symbol every 250′ (cycle track) |
| Crosswalk | EA | 4 | $1,000.00 | $4,000 | 4 Crosswalks per mile, 36′ x 10′, High Visibility |
| Retaining Wall (up to 6′ height) | LF | 528 | $500.00 | $264,000 | 10% of length |
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of road |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Landscaping (5%) | LS | 1.00 | $39,233.00 | $39,233 | |
| Drainage and E&S (10%) | LS | 1.00 | $78,467.00 | $78,467 | |
| Maintenance of Traffic (10%) | LS | 1.00 | $78,467.00 | $78,467 | |
| Utility Adjustments (10%) | LS | 1.00 | $78,467.00 | $78,467 | |
| Subtotal | $1,059,301 | ||||
| 30% Contingency | $317,790 |
Total Estimated Cost: $1,377,100 –> $260.81 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Earthwork, Excavation, Grading, Fill | CY | 9,387 | $17.00 | $159,573 | 12′ disturbance each side and 2′ depth |
| Aggregate Base Course | CY | 2,738 | $25.00 | $68,444 | 7′ width each side and 1′ depth |
| Asphalt Surface Course | TON | 695 | $67.00 | $46,547 | 7′ width and 0.125′ depth, 13.3 CF in a TON |
| Asphalt Base Course | TON | 2,779 | $67.00 | $186,189 | 7′ width and 0.5′ depth, 13.3 CF in a TON |
| Retaining Wall (up to 6′ height) | LF | 528 | $500.00 | $264,000 | 10% of length |
| Remove Curb and Gutter | LF | 10,560 | $7.00 | $73,920 | both sides |
| Remove 6′ sidewalk | SY | 7,040 | $4.00 | $28,160 | both sides |
| Curb and Gutter | LF | 10,560 | $20.00 | $211,200 | both sides |
| Construct Concrete Sidewalk (4″ Thickness) | SY | 5,867 | $58.00 | $340,267 | both sides |
| Thermoplastic Pavement Marking Symbol | EA | 40 | $275.00 | $11,000 | 1 Symbol every 250′ (cycle track) |
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of road |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Landscaping (5%) | LS | 1.00 | $69,711.00 | $69,711 | |
| Drainage and E&S (10%) | LS | 1.00 | $139,422.00 | $139,422 | |
| Maintenance of Traffic (10%) | LS | 1.00 | $139,422.00 | $139,422 | |
| Utility Adjustments (10%) | LS | 1.00 | $139,422.00 | $139,422 | |
| Subtotal | $1,882,198 | ||||
| 30% Contingency | $564,659 |
Total Estimated Cost: $2,446,900 –> $463.43 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Earthwork, Excavation, Grading, Fill | CY | 15,644 | $17.00 | $265,956 | 20′ disturbance one side and 2′ depth |
| Aggregate Base Course | CY | 1,956 | $25.00 | $48,889 | 10′ width and 1′ depth |
| Asphalt Surface Course | TON | 496 | $67.00 | $33,248 | 10′ width and 0.125′ depth, 13.3 CF in a TON |
| Asphalt Base Course | TON | 1,985 | $67.00 | $132,992 | 10′ width and 0.5′ depth, 13.3 CF in a TON |
| Retaining Wall (up to 6′ height) | LF | 528 | $500.00 | $264,000 | 10% of length |
| Remove Curb and Gutter | LF | 5,280 | $7.00 | $39,960 | one side |
| Remove 6′ sidewalk | SY | 3,520 | $4.00 | $14,080 | one side |
| Curb and Gutter | LF | 5,280 | $20.00 | $105,600 | one side |
| Construct Concrete Sidewalk (4″ Thickness) | SY | 2,933 | $58.00 | $170,133 | one side |
| Thermoplastic Pavement Marking Symbol | EA | 40 | $275.00 | $11,000 | 1 Symbol every 250′ (cycle track) |
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of road |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Landscaping (5%) | LS | 1.00 | $54,389.00 | $54,389 | |
| Drainage and E&S (10%) | LS | 1.00 | $108,778.00 | $108,778 | |
| Maintenance of Traffic (10%) | LS | 1.00 | $108,778.00 | $108,778 | |
| Utility Adjustments (10%) | LS | 1.00 | $108,778.00 | $108,778 | |
| Subtotal | $1,468,501 | ||||
| 30% Contingency | $440,550 |
Total Estimated Cost: $1,909,100 –> $361.57 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost |
|---|---|---|---|---|
| Basic Prefab Bridge (200′ span) | SF | 2,800 | $250.00 | $700,000 |
| Public Art Bridge (200′ span) | SF | 2,800 | $1,000.00 | $2,800,000 |
Total Estimated Cost: $3,500,000 –> $17,500.00 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Thermoplastic Pavement Marking Lines (4″ to 6″) | LF | 2,400 | $1.75 | $4,200 | 4 dotted lines, 30′ length either side of symbol |
| Thermoplastic Pavement Marking Symbol | EA | 80 | $275.00 | $22,000 | 1 Symbol every 125′ per side of the road |
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of road |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Maintenance of Traffic (10%) | LS | 1.00 | $0.00 | $0 | |
| Subtotal | $31,120 | ||||
| 20% Contingency | $6,224 |
Total Estimated Cost: $37,400 –> $7.08 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Thermoplastic Pavement Marking Lines (4″ to 6″) | LF | 2,400 | $1.75 | $4,200 | 4 dotted lines, 30′ length either side of symbol |
| Thermoplastic Pavement Marking Symbol | EA | 80 | $275.00 | $22,000 | 1 Symbol every 125′ per side of the road |
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of road |
| Green coloring within sharrow space | SF | 9,600 | $6.00 | $57,620 | 4′ wide color, 30′ length either side of symbol |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Maintenance of Traffic (10%) | LS | 1.00 | $0.00 | $0 | |
| Subtotal | $88,720 | ||||
| 20% Contingency | $17,744 |
Total Estimated Cost: $106,500 –> $20.17 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Thermoplastic Pavement Marking Lines (4″ to 6″) | LF | 10,560 | $1.75 | $18,480 | 2 solid lines entire length |
| Thermoplastic Pavement Marking Symbol | EA | 0 | $275.00 | $0 | no symbols |
| New Sign | EA | 20 | $246.00 | $4,920 | 1 Sign every 500′, each side of road |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Maintenance of Traffic (10%) | LS | 1.00 | $2,340.00 | $2,340 | |
| Subtotal | $25,740 | ||||
| 20% Contingency | $5,148 |
Total Estimated Cost: $30,900 –> $5.85 Per Foot
| Item | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Street Light Pedestal | EA | 88 | $1,000.00 | $88,000 | new pedestrian poles, lights, one side, 60′ spacing |
| Pedestrian Scale Lighting | EA | 88 | $8,500.00 | $746,000 | |
| Power Hookup | EA | 1 | $50,000.00 | $50,000 |
| Lump Sum Items | Unit | Quantity | Unit Cost | Total Cost | Assumptions |
|---|---|---|---|---|---|
| Landscaping (5%) | LS | 1.00 | $44,300.00 | $44,300 | |
| Drainage and E&S (10%) | LS | 1.00 | $88,600.00 | $88,600 | |
| Maintenance of Traffic (10%) | LS | 1.00 | $88,600.00 | $88,600 | |
| Utility Adjustments (10%) | LS | 1.00 | $88,600.00 | $88,600 | |
| Subtotal | $1,196,100 | ||||
| 30% Contingency | $358,830 |
Total Estimated Cost: $1,555,000 –> $294.51 Per Foot, $3,110,000 –> Two Sides of Road