v1ch6
Report of the PRESIDENTIAL COMMISSION
on the Space Shuttle Challenger Accident
Chapter VI: An Accident Rooted in
History.
Early Design
120
] The Space Shuttle's
Solid Rocket Booster problem began with the faulty design of its
joint and increased as both NASA and contractor management first
failed to recognize it as a problem, then failed to fix it and
finally treated it as an acceptable flight risk.
Morton Thiokol, Inc., the contractor, did not
accept the implication of tests early in the program that the design
had a serious and unanticipated flaw.
NASA did not accept the judgment of its engineers that
the design was unacceptable, and as the joint problems grew in number
and severity NASA minimized them in management briefings and reports.
Thiokol's stated position was that "the condition is
not desirable but is acceptable."
Neither Thiokol nor NASA expected the rubber
O-rings sealing the joints to be touched by hot gases of motor
ignition, much less to be partially burned. However, as tests and
then flights confirmed damage to the sealing rings, the reaction by
both NASA and Thiokol was to increase the amount of damage considered
"acceptable." At no time did management either recommend a redesign
of the joint or call for the Shuttle's grounding until the problem
was solved.
Thiokol was selected to receive the NASA
contract to design and build the Solid Rocket Boosters on November
20, 1973.
The booster was the largest Solid
Rocket Motor ever produced in the United States; it was also the
first solid motor program managed by NASA's Marshall Space Flight
Center in Huntsville, Alabama.
Costs were the primary concern of NASA's
selection board, particularly those incurred early in the
program.
Thiokol's three competitors were Aerojet Solid
Propulsion Co., Lockheed Propulsion Co. and United Technologies. The
Source Evaluation Board on the proposals rated Thiokol fourth under
the design, development and verification factor, second under the
manufacturing, refurbishment and product support factor and first
under the management factor.
Thiokol received the second highest overall
Mission Suitability score, tied with United
Technologies.
In a December 12, 1973, report, NASA selection
officials said Thiokol's "cost advantages were substantial and
consistent throughout all areas evaluated."
They also singled out Thiokol's joint design for
special mention.
"The Thiokol motor case joints utilized dual
O-rings and test ports between seals, enabling a simple leak check
without pressurizing the entire motor," the officials' report said.
"This innovative design feature increased reliability and decreased
operations at the launch site, indicating good attention to low cost
(design, development, testing and engineering) and production."
"We noted that the [NASA Source Selection]
board's analysis of cost factors indicated that Thiokol could do a
more economical job than any of the other proposers in both the
development and the production phases of the program; and that,
accordingly, the cost per flight to be expected from a Thiokol-built
motor would be the lowest," the officials said. "We, therefore,
concluded that any selection other than Thiokol would give rise to an
additional cost of appreciable size."
The Selection officials said they "found no
other [
121
] factors bearing upon the selection that ranked in
weight with the foregoing."
Cost consideration overrode any other-
objections, they decided. We concluded that the main criticisms of
the Thiokol proposal in the Mission Suitability evaluation were
technical in nature, were readily correctable, and the costs to
correct did not negate the sizable Thiokol cost advantage," the
selection officials concluded.
The cost-plus-award-fee contract, estimated to
be worth $800 million, was awarded to Thiokol.
The design of the Shuttle Solid Rocket Booster
was primarily based on the Air Force's Titan III solid rocket, one of
the most reliable ever produced. Thiokol hoped to reduce new design
problems, speed up the development program and cut costs by borrowing
from the Titan design. In Thiokol's Solid Rocket Motor proposal, the
rocket fuel is contained in four- forged steel cases which are
stacked one on top of the other. The casings were connected by a
circumferential tang and clevis, as were the
Titans.
10
Despite their many similarities, the Thiokol
Solid Rocket Booster and the Titan motors had some significant design
differences. For example, the joints of the Titan were designed so
that the insulation of one case fits tightly against the insulation
of the adjacent case to form a more gastight fit than the Thiokol
design. One O-ring bore seal was used in each Titan joint to stop any
hot gas pressure that might pass by the insulation overlap,
11
but in the Titan design the O-ring was able but not
intended to take the brunt of the combustion pressure. In contrast,
the Thiokol O-rings were designed to take the brunt of the combustion
pressure, with no other gas barriers present except an insulating
putty. Also, the Solid Rocket Motor joint had two O-rings, the second
to provide a backup in case the primary seal failed.
Asbestos-filled putty was used in the Solid
Rocket Motor to pack the space between the two case segments to
prevent O-ring damage from the heat of combustion gases.
12
Thiokol believed the putty was plastic, so when acted
on by the combustion pressure at the motor's ignition the putty flow
towards the O-ring would compress the air in the gap between the
putty and the primary O-ring.
13
The compressed air, in turn, would.....
Figure 1.
Comparison of Original Design to Design Used.
122
] ...cause the
primary O-ring to extrude into the gap between the clevis and the
tang, behind the primary O-ring groove, thereby sealing the opening.
If the primary O-ring did not seal, the intent was that the secondary
would pressurize and seal the joint by extruding into the gap behind
its groove.
14
Another difference in the Solid Rocket Motor
and the Titan was that the tang portion of the Thiokol joint was
longer in order to accommodate two O-rings instead of one. It was
more susceptible to bending under combustion pressure than the Titan
joint, as post-design tests and later flight experience
demonstrated.
15
The initial Thiokol design proposal was
changed before the production motors were manufactured. Originally,
the joint seal design incorporated both a face seal and a bore
seal.
16
Figure
.) However, the motor that was
eventually used had double bore O-rings. The original bore seal/face
seal design was chosen because it was anticipated that it "provides
[better] redundance over a double bore ring seal since each is
controlled by different manufacturing tolerances, and each responds
differently during joint assembly. "
17
Because the early design incorporated tolerances
similar to the Titan and it also incorporated a face seal, Thiokol
believed it possessed "complete, redundant seal capability."
18
Nevertheless, as the Solid Rocket Motor
program progressed, Thiokol-with NASA's concurrence-dropped the
face/bore seal design for one using a double bore seal (
Figure 1
). NASA engineers at Marshall said the original design
would have required tapered pins to maintain necessary tolerances and
assure enough"squeeze" on the face-sealing
O-ring.
19
However, design analysis determined that motor
ignition would create tension loads on the joint sufficient to cause
the tapered pins to pop out. Solving that would have meant designing
some type of pin-retainers. Moreover, the rocket assembly was much
easier with the dual bore seals. Because inspections and tests had to
be conducted on the Solid Rocket Motor stack, horizontal assembly was
required. Thiokol engineer, Howard McIntosh, described this in a
Commission interview on April 2, 1986:
"We were concerned very much about
the horizontal assembly that we had to do to do the static tests. The
Titan had always been assembled vertically, and so there had never
been a larger rocket motor to our knowledge that was assembled
(horizontally)".
20
Because of the extremely tight tolerances in
the joints caused by horizontal assembly, McIntosh noted, "We . . .
put the bore seals in there, and we opened the tolerance in the gaps
slightly to accommodate that."
21
To tighten the joint's fit and to increase the squeeze
in the O-rings to compensate for the larger tolerances, Thiokol
subsequently put thin metal shims between the outer walls of the tang
and clevis.
Another significant feature of the Thiokol
design was a vent, or port, on the side of the motor case used after
assembly to check the sealing of the O-rings. As will be noted later,
this leak check eventually became a significant aspect of the O-ring
erosion phenomenon.
22
The manufacture of the O-rings themselves
constituted another difference between the Titan and the Thiokol
Solid Rocket Motor. While both O-rings were Viton rubber, the Titan
O-rings were molded in one piece. The Solid Rocket Motor O-rings were
made from sections of rubber O-ring material glued together. The
specifications allowed five such joints, a number chosen arbitrarily,
and the vendor routinely made repairs of voids and inclusions after
getting the material supplies. Only surface inspections were
performed by Thiokol and by the manufacturer.
Finally, unlike the Titan, the Thiokol Solid
Rocket Motor was designed for multiple firings. To reduce program
costs, each Thiokol motor case for the Shuttle was to be recovered
after flight and reused up to 20 times.
23
Early Tests
Thiokol began testing the Solid Rocket Motor
in the mid-1970's. One of the early important tests was a 1977
"hydroburst test."
24
Its purpose was to test the strength of the
steel cases by simulating a motor firing. The case was pressurized
with water to about one and one-half times the pressure of an ignited
motor (about 1,500 pounds per square inch) to make certain the case
had adequate structural margin.
25
Also, to measure the pressure between the O-rings,
engineers attached instruments to the leak test port at a segment
joint. Although the test was successful in that it demonstrated the
case met strength requirements, test measurements showed that,
contrary to design expectations, the joint [
123
] tang and inside
clevis bent away from each other instead of toward each other and by
doing so reduced-instead of increased-pressure on the 0-ring in the
milliseconds after ignition.
26
This phenomenon was called "joint rotation."
Testifying before the Commission, Arnold Thompson, Thiokol's
supervisor of structures, said,
"We discovered that the joint was
opening rather than closing as our original analysis had indicated,
and in fact it was quite a bit. I think it was up to 52
onethousandths of an inch at that time, to the primary
O-ring."
27
Thiokol reported these initial test findings
to the NASA program office at Marshall. Thiokol engineers did not
believe the test results really proved that "joint rotation" would
cause significant problems,
28
and scheduled
no additional tests for the specific purpose of confirming or
disproving the joint gap behavior.
Design Objections
Reaction from Marshall to the early Solid
Rocket Motor test results was rapid and totally opposite of
Thiokol's. In a September 2, 1977 memorandum, Glenn Eudy, Marshall's
Chief Engineer of the Solid Rocket Motor Division, informed Alex
McCool, Director of the Structures and Propulsion Laboratory, that
the assembly of a developmental motor provided early indications that
the Thiokol design:
"Allowed O-ring clearance.... Some
people believe this design deficiency must be corrected by some
method such as shimming and perhaps design modification to the case
joint for hardware which has not been final machined.... I personally
believe that our first choice should be to correct the design in a
way that eliminates the possibility of O-ring clearance.... Since
this is a very critical SRM issue, it is requested that the
assignment results be compiled in such a manner as to permit review
at the S&E Director's level as well as project manager."
After seeing the data from the September 1977
hydroburst test, Marshall engineer Leon Ray submitted a report
entitled "Solid Rocket Motor Joint Leakage Study" dated October 21,
1977. It characterizes "no change" in the Thiokol design as
"unacceptable"-"tang can move outboard and cause excessive joint
clearance resulting in seal leakage. Eccentric tang/clevis interface
can cause O-ring extrusion when case is pressurized." Ray recommended
a "redesign of the tang and reduce tolerance on the clevis" as the
"best option for a long-term fix."
29
After Ray's 1977 report, John Q. Miller, chief
of the Solid Rocket Motor branch at Marshall, signed and sent a
memorandum on January 9, 1978 to his superior, Glenn Eudy, describing
the problems evident in the Solid Rocket Motor joint seal. "We see no
valid reason for not designing to accepted standards," the memo said,
and it emphasized that proper sealing of the joint by use of shims to
create necessary O-ring pressure was "mandatory to prevent hot gas
leaks and resulting catastrophic failure."
30
One year later, not having received a response
to his 1978 memo, Miller signed and forwarded a second memo
strenuously objecting to Thiokol's Solid Rocket Motor joint seal
design. This memo, dated January 19, 1979, opened with: "We find the
Thiokol position regarding design adequacy of the clevis joint to be
completely unacceptable...."
31
The memorandum made three principal objections to
Thiokol's joint design. The first was the "large sealing surface gap
created by extensive tang/clevis relative movement." The memo said
this movement, the so-called"joint rotation," caused the primary
O-ring to extrude into the gap, "forcing the seal to function in a
way which violates industry and government O-ring application
practices."
32
Moreover, joint rotation allowed the secondary O-ring
to "become completely disengaged from its sealing surface on the
tang." Finally, the memorandum noted that although Thiokol's contract
required all high pressure case seals to be verifiable, "the clevis
joint secondary O-ring seal has been verified by tests to be
unsatisfactory."
33
A copy of the second memorandum was sent to George
Hardy, then Solid Rocket Booster project manager at Marshall. Thiokol
apparently did not receive copies of either Miller memorandum, and no
reply from Eudy to Miller has been found.
The Commission has learned that Leon Ray
actually authored the Miller memos to Eudy, although Miller signed
them and concurred in the objections raised.
34
During February, 1979, Ray also reported on a visit he
made to two O-ring manufacturers-the Precision Rubber Products
Corporation at Lebanon Tennessee, and the Parker Seal Co. at
Lexington, Kentucky.
35
Eudy [
124
] accompanied Ray on
the Precision visit. The purpose of the trips was to give the
manufacturers the data on the O-ring experiences at Thiokol and to
"seek opinions regarding potential risks involved," Ray wrote in a
February 9, 1979, memo describing the visit. Officials at Precision
did "voice concern for the design, stating that the Solid Rocket
Motor O-ring extrusion gap was larger than that covered by their
experience," Ray reported. "Their first thought was that the O-ring
was being asked to perform beyond its intended design and that a
different type of seal should be considered," Ray
added.
36
During the Commission hearing on May 2, 1986,
Ray was asked why the 1978 and 1979 memoranda were written:
Mr. Ray
: The
reason they were written was as a result of test data that we had,
and I have to go back to, I guess, a little bit further back in time
than these memos. When the joint was first designed, the analysis
produced by Thiokol says the joint would close, the extrusion gap
would actually close.
We had quite a debate about that until we did
a test on the first couple of segments that we received from the
manufacturer, which in fact showed that the joint did open. Later on
we did some tests with the structural test article, and this is
mentioned in the memo as STA-1 [Structural Test Article].
At that time, we really nailed it down. We got
some very accurate numbers on joint rotation, and we know for a fact
that during these tests that, just what the memo says, the joint
rotated. The primary O-ring was extruded up into the joint. The
secondary O-ring did in fact detach from the
seat.
37
No records show Thiokol was informed of the
visits, and the O-ring design was not changed.
Thiokol's phase 1 certification review on
March 23, 1979, mentioned leak check failures, and forces during case
joint assembly that resulted in clevis O-ring grooves not conforming
with tang sealing surfaces. However, this was not listed as a problem
or a failure.
38
Verification and Certification
Committee
While Ray was warning of problems with joint
rotation, static motor tests in July 1978 and April 1980 again were
demonstrating that inner tang/clevis relative movement was greater
than originally predicted.
39
Thiokol continued to question the validity of these
joint rotation measurements and their effect on the availability of
the secondary O-ring.
In 1980, NASA empanelled a Space Shuttle
Verification/Certification Committee to study the flight worthiness
of the entire Shuttle system. A subdivision of that group, the
Propulsion Committee, met with NASA Solid Rocket Motor program
personnel and raised several concerns about the joint
design.
40
The Committee pointed out that the booster's leak test
pressurized the primary O-ring in the wrong direction so that the
motor ignition would have to move the ring across its groove before
it sealed. The Committee added that the effect of the insulation
putty was not certain. Redundancy of the O-rings was also listed as a
verification concern. The same report, however, said "the Committee
understands from a telecon that the primary purpose of the second
O-ring is to test the primary and that redundancy is not a
requirement." George Hardy testified that the Committee's statement
conflicted with his understanding:
"The discussion there or the
reference there to a telecon-and I don't know who that was with-that
implies there was no intent for the joint to be redundant is totally
foreign to me. I don't know where they would have gotten that
information because that was the design requirement for the joint."
41
In May 1980, the Verification/Certification
Committee recommended that NASA conduct full-scale tests to verify
the field joint integrity, including firing motors at a mean bulk
propellant temperature range of 40-90 degrees Fahrenheit. The panel
also asked NASA to:
"Perform case burst test with one
O-ring removed. During the burst test for final verification of the
motor case safety factor, one of the two O-rings failed by extrusion
and leaked. The analysis used for additional verification did not
include further gap openings caused by joint deflection at
pressurization or any deflections caused by bending loads. The panel
considers the above to be inadequate to provide operational program
reliability, and marginal to provide adequate [
125
] safety factor
confidence on [Shuttle flight] one."
42
The NASA program response to these issues was
included in the final Committee report in September 1980. It said
that the original hydroburst tests and the lightweight case tests,
being conducted at the time, satisfied the intent of the Committee's
recommendations. Moreover, the response stated: "NASA specialists
have reviewed the field joint design, updated with larger O-rings and
thicker shims and found the safety factors to be adequate for the
current design. Re-analysis of the joint with larger O-rings and
thicker shims is being accomplished as part of the lightweight case
program.... The joint has been sufficiently verified with the testing
accomplished to date (joint lab tests, structural test article, and
seven static firings and the two case configuration burst tests) and
currently scheduled for lightweight case
program."
43
Criticality Classification and
Changes
The Solid Rocket Motor certification was
deemed satisfactory by the Propulsion Committee of the
Verification/Certification Group on September 15, 1980. Shortly
thereafter, on November 24, 1980, the Solid Rocket Booster joint was
classified on the Solid Rocket Booster Critical Items List as
criticality category 1 R. NASA defines "Criticality 1R" as any
subsystem of the Shuttle that contains "redundant hardware, total
element failure of which could cause loss of life or
vehicle."
44
The use of "R", representing redundancy, meant that
NASA believed the secondary O-ring would pressurize and seal if the
primary O-ring did not. Nonetheless, the 1980 Critical Items List
(CIL) states:
"Redundancy of the secondary field
joint seal cannot be verified after motor case pressure reaches
approximately 40 percent of maximum expected operating pressure. It
is known that joint rotation occurring at this pressure level with a
resulting enlarged extrusion gap causes the secondary O-ring to lose
compression as a seal. It is not known if the secondary O-ring would
successfully reseal if the primary O-ring should fail after motor
case pressure reaches or exceeds 40 percent of maximum expected
operating pressure."
When asked about the text of the 1980
Criticality 1R classification, Arnold Aldrich, NASA Manager of the
National Space Transportation System, said,
"The way that . . . language
[reads], I would call it [criticality] 1."
45
Notwithstanding this apparent contradiction in
the classification 1R and the questionable status of the secondary
described in the text of the CIL, the joint carried a 1 R
classification from November 1980 through the flight of STS-5
(November 1982).
The Space Shuttle first flew on April 12-14,
1981. After the second flight, STS-2, in November 1981, inspection
revealed the first in-flight erosion of the primary
O-ring.
46
It occurred in the right Solid Rocket Booster's aft
field joint and was caused by hot motor gases.
47
The damage to the ring proved to be the worst ever
found on a primary O-ring in a field joint on any recovered Solid
Rocket Booster.
48
Post-flight examination found an erosion depth of .053
inches on the primary O-ring; nonetheless, the anomaly was not
reported in the Level I Flight Readiness Review for STS-3 held on
March 9, 1982. Furthermore, in 1982 the STS-2 O-ring erosion was not
reported on the Marshall problem assessment system and given a
tracking number as were other flight anomalies.
49
In mid- 1982, two significant developments
took place. Because Thiokol believed blow holes in the insulating
putty were a cause of the erosion on STS-2,
50
they began tests of the method of putty layup and the
effect of the assembly of the rocket stages on the integrity of the
putty. The manufacturer of the original putty, Fuller-O'Brien,
discontinued the product and a new putty, from the Randolph Products
Company, was tested and selected in May 1982.
51
The new Randolph putty was eventually substituted for
the old putty in the summer of 1983, for the STS-8 Solid Rocket Motor
flow.
52
A second major event regarding the joint seal
occurred in the summer of 1982. As noted before, in 1977-78, Leon Ray
had concluded that joint rotation caused the loss of the secondary
O-ring as a backup seal. Because of May 1982 high pressure O-ring
tests and tests of the new lightweight motor case, Marshall
management [
126
] finally accepted the conclusion that the secondary
O-ring was no longer functional after the joints rotated when the
Solid Rocket Motor reached 40 percent of its maximum expected
operating pressure. It obviously followed that the dual O-rings were
not a completely redundant system, so the Criticality 1R had to be
changed to Criticality 1.
53
This was done at Marshall on December 17, 1982. The
revised Critical Items List read (See pages 157 and 158):
"Criticality Category 1.
"Failure Mode and Causes: Leakage at case
assembly joints due to redundant O-ring seal failures or primary seal
and leak check port O-ring failure.
"Note. Leakage of the primary O-ring seal
is classified as a single-failure point due to possibility of loss of
sealing at the secondary O-ring because of joint rotation after motor
pressurization.
"Failure Effect Summary: Actual Loss-
Loss of mission, vehicle and crew due
to metal erosion, burn through, and probable case burst resulting in
fire and deflagration. .
"Rationale for Retention:
"The Solid Rocket Motor case joint design is
common in the lightweight and regular weight cases having identical
dimensions. The joint concept is basically the same as the single
O-ring joint successfully employed on the Titan III Solid Rocket
Motor.... On the Shuttle Solid Rocket Motor, the secondary O-ring was
designed to provide redundancy and to permit a leak check, ensuring
proper installation of the O-rings. Full redundancy exists at the
moment of initial pressurization. However, test data shows that a
phenomenon called joint rotation occurs as the pressure rises,
opening up the O-ring extrusion gap and permitting the energized ring
to protrude into the gap. This condition has been shown by test to be
well within that required for safe primary O-ring sealing. This gap
may, however, in some cases, increase sufficiently to cause the
unenergized secondary O-ring to lose compression, raising question as
to its ability to energize and seal if called upon to do so by
primary seal failure. Since, under this latter condition only the
single O-ring is sealing, a rationale for retention is provided for
the simplex mode where only one O-ring is acting" [emphasis added] .
54
The retention rationale for the "simplex" or
single O-ring seal was written on December 1, 1982, by Howard
McIntosh, a Thiokol engineer.
55
This document gave the justification for flight with
the single functional O-ring. It reported that tests showed the
Thiokol design should be retained, citing the Titan history, the leak
and hydroburst tests, and static motor firings as justification.
However, it also contained the following rationale which appeared to
conflict with the Criticality 1 classification that the secondary
O-ring was not redundant:
"Initial information generated in
a lightweight cylinder-to-cylinder proof test shows a total movement
of only .030 inch at pounds per square inch, gauge pressure in the
center joint. This . . . indicates that the tang-to-clevis movement
will not unseat the secondary O-ring at operating
pressures."
56
Testimony in hearings and statements given in
Commission interviews support the view that NASA management and
Thiokol still considered the joint to be a redundant seal even after
the change from Criticality 1R to 1. For example, McIntosh's
interview states:
Question
[After the Criticality I classification], what did you think it would
take to make [the joint seal] 1R?
Mr. McIntosh
: I thought it was already 1R. I thought that after
those tests that would have been enough to do it.
Question
Well, you knew it was 1 but you were hoping for 1R?
Mr McIntosh
Yeah, I was hoping for 1R, and I thought this test data would do it,
but it didn't.
57
At the time (in 1982-83), the redundancy of
the secondary O-ring was analyzed in terms of joint or hardware
geometry, with no consideration being given to the resiliency of the
ring as affected by temperatures.
58
Moreover, Marshall engineers like Ray and Miller
disagreed with Thiokol's calculations on the measurement of joint
opening.
59
That engineering debate eventually went to a "referee"
for testing which was not concluded until after the 51-L
accident.
127
] Notwithstanding the
view of some of Marshall engineers that the secondary ring was not
redundant, even at the time of the Criticality revision, Marshall
Solid Rocket Motor program management appeared to believe the seal
was redundant in all but exceptional cases. Dr. Judson Lovingood told
the Commission:
" . . . [T]here are two conditions
you have to have before you don't have redundancy. One of them is
what I call a spatial condition which says that the dimensional
tolerances have to be such that you get a bad stackup, you don't have
proper squeeze, etc. On the O-ring so that when you get joint
rotation, you will lift the metal surfaces off the O-ring. All right,
that's the one condition, and that is a worst case condition
involving dimensional tolerances.
"The other condition is a temporal condition
which says that you have to be past a point of joint rotation, and of
course, that relates back to what I just said.
"So first of all, if you don't have this bad
stackup, then you have full redundancy. Now, secondly, if you do have
the bad stackup, you had redundancy during the ignition transient up
to the 170 millisecond point, whatever it is, but that is the way I
understand the [Critical Items List]."
60
George Hardy and Lawrence Mulloy shared
Lovingood's view that the secondary seal was redundant in all but
situations of worst case tolerances.
61
However, there is no mention of this caveat in the
Critical Items List itself, nor does it appear in the subsequent
"waiver" of the Criticality 1 status granted by NASA Levels I and II
in March, 1983.
62
This waiver was approved to avoid the obligations
imposed on the Shuttle Program by Paragraph 2.8 of the Space Shuttle
Program Requirements Document, Level I, dated June 30, 1977. That
paragraph states:
"The redundancy requirements for
all flight vehicle subsystems (except primary structure, thermal
protection system, and pressure vessels) shall be established on an
individual subsystems basis, but shall not be less than fail-safe.
'Fail-safe' is defined as the ability to sustain a failure and retain
the capability to successfully terminate the mission. Redundant
systems shall be designed so that their operational status can be
verified during ground turnaround and to the maximum extent possible
while in flight."
63
Glynn Lunney, the former manager of the STS
Program (Level II at JSC) described the Criticality 1 change and
resulting waiver to the Commission on May 2:
Mr. Lunney
: Well, the approval of the waiver in March of 83, at
the time I was involved in that. I was operating on the assumption
that there really would be redundancy most of the time except when
the secondary O-ring had a set of dimensional tolerances add up, and
in that extreme case there would not be a secondary seal.
So I was dealing with what I thought was a
case where there were two seals unless the dimensional tolerances
were such that there might only be one seal in certain cases.
Chairman Rogers
: Now, to me, if you will excuse the expression, that
sounds almost contradictory, what you just said. What you first said
was you came to the conclusion that you could only rely on the
primary seal and therefore you removed the R.
Mr. Lunney
Yes, sir.
Chairman Rogers
: And now you're saying, if I understand it, that
experience showed that there was redundancy after all.
Mr. Lunney
No, I don't know of any experience showing that. What I'm saying is
that the removal of the R is an indicator that under all
circumstances we did not have redundancy. There were a certain number
of cases under which we would not have redundancy of the secondary
O-ring.
Recognizing that, even though there were a lot
of cases where we expected we would have redundancy we changed the
criticality designation.
Chairman Rogers
: It was saying to everybody else you can't necessarily
rely on the primary seal, and if the primary seal fails, as you've
said here, there may be loss of vehicle, mission and crew.
Mr. Lunney
I would adjust that to only say you cannot rely on the secondary
O-ring [
128
] but we would expect the primary O-ring to always be
there.
64
The criticality waiver was processed outside
the formal NASA Program Requirements Control Board, however,
representatives of that group "signed off" on the
document.
65
It was forwarded to Level I and approved by Associate
Administrator for Space Flight (Technical), L. Michael Weeks on March
28, 1983. Weeks told the Commission he signed the waiver because of
the Certification/Verification Review of the Propulsion Committee in
1980. Weeks explained, "We felt at the time-all of the people in the
program I think felt that this Solid Rocket Motor in particular or
the Solid Rocket Booster was probably one of the least worrisome
things we had in the program."
66
The waiver was signed less than one week prior to the
launch of STS-6 on April 4. According to interviews of Arnold Aldrich
and of Richard Kohrs, the latter having been involved with the waiver
review at Johnson Level II, the waiver was approved so that STS-6
could fly.
67
However, Weeks denied any connection between the Level
I waiver approval and the flight of STS-6.
68
Although some Thiokol engineers and officials
claimed that they had no notice of the Criticality change and waiver
in December, 1982 and in March, 1983, from the approval signatures
(including Thiokol's Operations Manager at Marshall, Maurice Parker)
and the distribution of the Criticality and Waiver documents,
apparently Thiokol officials were sent copies and were involved in
the criticality reclassification.
69
Nonetheless, the Commission has also determined that
several documents tracking the O-ring erosion at Thiokol and Marshall
refer to the Solid Rocket Motor field joint seal as Criticality 1-R,
long after the status was changed to Criticality 1.
70
STS 41-B O-Ring Erosion
As
Figure 2
shows,
71
prior to STS 41-B, the O-ring erosion/blow-by problem
was infrequent, occurring on a field joint of STS-2 (November, 1981),
nozzles of STS-6 (April, 1983) and a nozzle of QM-4 (March, 1983), a
qualification test motor fired by Thiokol.
72
However, when STS 41-B flew on February 3, 1984, the
left Solid Rocket Booster forward field joint and the right nozzle
joint primary O-rings both suffered erosion damage. Thiokol engineers
reacted to this discovery by filing a problem report on the O-ring
erosion found on STS 41 -B. Thiokol presented a series of charts to
the Marshall Solid Rocket Booster Engineering Office about the 41-B
O-ring erosion. Thiokol told Marshall that recent joint rotation
measurements in tests indicated the secondary O-ring will not unseat,
providing confidence that the secondary was an adequate backup. Keith
Coates described his view about Thiokol's data in a February 29, 1984
memorandum to George Hardy:
"We have two problems with their
rationale. The effect of 0.065 inch erosion on O-ring sealing
capability is not addressed. We have asked Thiokol to provide their
data to justify their confidence in the degraded O-ring. The second
concern is the amount of joint rotation. L. Ray does not agree with
Thiokol numbers, and he has action to discuss his concern with R.
Boisjoly (Thiokol) and reach agreement.
"Thiokol definition of their plans on
resolution of the problem is very weak."
The erosion problem was identified and tracked
by the Marshall Problem Assessment System as Marshall Record A07934
and by Thiokol as Thiokol Contractor Record DR4-5/30, "Slight char
condition on primary O-ring seal in forward field joint on SRM A57 of
STS-11 flight, Mission 41B."
73
The Marshall Problem Assessment System Report
states:
"Remedial action-none required;
problem occurred during flight. The primary O-ring seal in the
forward field joint exhibited a charred area approximately 1 inch
long .03-.050 inches deep and .100 inches wide. This was discovered
during post-flight segment disassembly at KSC."
A March 8, 1984 entry on the same report
continues:
"Possibility exists for some
O-ring erosion on future flights. Analysis indicates max erosion
possible is .090 inches according to Flight Readiness Review findings
for STS-13. Laboratory test shows sealing integrity at 3,000 psi
using an O-ring with simulated erosion depth of .095 inches
Therefore, this is not a constraint to future launches."
74
129-131
] Figure 2.
O-Ring Anomalies Compared with Joint
Temperature and Leak Check Pressure
Flight or
Motor
Date
(Solid Rocket
Booster)
Joint/O-Ring
Pressure
(psi)
Erosion
Blow-by
Joint Temp
°F
Field
Nozzle
DM-1
07/18/77
NA
NA
84
DM-2
01/18/78
NA
NA
49
DM-3
10/19/78
NA
NA
61
DM-4
02/17/79
NA
NA
40
QM-1
07/13/79
NA
NA
83
QM-2
09/27/79
NA
NA
67
QM-3
02/13/80
NA
NA
45
STS-1
04/12/81
50
50
66
STS-2
11/12/81
(Right)
Aft Field/Primary
50
50
70
STS-3
03/22/81
50
50
NA
NA
80
STS-4
06/27/82
Unknown: hardware lost at
sea
50
50
NA
NA
80
DM-5
10/21/82
NA
NA
58
STS-5
11/11/82
50
50
68
QM-4
03/21/83
Nozzle/Primary
NA
NA
60
STS-6
04/04/83
(Right)
Nozzle/Primary
50
50
67
(Left)
Nozzle/Primary
50
50
67
STS-7
06/18/83
50
50
72
STS-8
08/30/83
100
50
73
STS-9
12/28/83
100
100
70
STS 41-B
02/03/84
(Right)
Nozzle/Primary
200
100
57
(Left)
Forward
Field/Primary
200
100
57
STS 41-C
04/06/84
(Right)
Nozle/Primary
200
100
63
(Left)
Aft Field/Primary
200
100
63
(Right)
Igniter/Primary
NA
NA
63
STS 41-D
08/30/84
(Right)
Forward
Field/Primary
200
100
70
(Left)
Nozzle/Primary
200
100
70
(Right)
Igniter/Primary
NA
NA
70
STS 41-G
10/05/84
200
100
67
DM-6
10/25/84
Inner Gasket/Primary
NA
NA
52
STS 51-A
11/08/84
200
100
67
STS 51-C
01/24/85
(Right)
Center Field/Primary
200
100
53
(Right)
Center
Field/Secondary
200
100
53
(Right)
Nozzle/Primary
200
100
53
(Left)
Forward
Field/Primary
200
100
53
(Left)
Nozzle/Primary
200
100
53
STS 51-D
04/12/85
(Right)
Nozzle/Primary
200
200
67
(Right)
Igniter/Primary
NA
NA
67
(Left)
Nozzle/Primary
200
200
67
(Left)
Igniter/Primary
NA
NA
67
STS 51-B
04/29/85
(Right)
Nozzle/Primary
200
100
75
(Left)
Nozzle/Primary
200
100
75
(Left)
Nozzle/Primary
200
100
75
DM-7
05/09/85
Nozzle/Primary
NA
NA
61
STS 51-G
06/17/85
(Right)
Nozzle/Primary
200
200
70
(Left)
Nozzle/Primary
200
200
70
(Left)
Igniter/Primary
NA
NA
70
STS 51-F
07/29/85
(Right)
Nozzle/Primary
200
200
81
STS 51-I
08/27/85
(Left)
Nozzle/Primary
200
200
76
STS 51-J
10/03/85
200
200
79
STS 61-A
10/30/85
(Right)
Nozzle/Primary
200
200
75
(Left)
Aft Field/Primary
200
200
75
(Left)
Center Field/Primary
200
200
75
STS 61-B
11/26/85
(Right)
Nozzle/Primary
200
200
76
(Left)
Nozzle/Primary
200
200
76
STS 61-C
01/12/86
(Right)
Nozzle/Primary
200
200
58
(Left)
Aft Field/Primary
200
200
58
(Left)
Nozzle/Primary
200
200
58
STS 51-L
01/28/86
200
200
31
Dash (-) denotes no
anomaly.
NA denotes not
applicable.
NOTE: A list of the sequence of
launches (1-25), identified by STS mission designation, is provided
on pages 4 thru 6.
On STS-6, both nozzles had a hot gas path
detected in the putty with an indication of heat on the primary
O-ring.
On STS-9, one of the right Solid Rocket
Booster field joints was pressurized at 200 psi after a
destack.
On STS 41-C, left aft field had a hot gas
path detected in the putty with an indication of heat on the
primary O-ring.
On a center field joint of STS 51-C, soot
was blown by the primary and there was a heat effect on the
secondary.
On STS 51-G, right nozzle has erosion in
two places on the primary O-ring.
On STS 51-F, right nozzle had hot gas
path detected in putty with an indication of heat on the primary
O-ring.
On STS 51-I, left nozzle had erosion in
two places on the primary O-ring.
132
] This last entry is
also a summary of the briefing given by Thiokol to Lawrence Mulloy
about the 41-B erosion at the Level III Flight Readiness Review for
STS 41-C held at Marshall on March 8, 1984. At that same briefing,
the Chief Engineer for United Space Boosters, George Morefield,
raised prior Titan experience with O-ring problems. He explained in a
memorandum to Mulloy the following day:
"I alluded to the Titan III SRM
history which is quite similar to the current STS Solid Rocket Motor
experience. Post-fire inspection of Titan Solid Rocket Motor static
test motors showed that pressurization of the single O-rings in the
pressure vessel routinely occurred via a single break-down path
across the joint putty. There was also evidence that some O-rings
never see pressure in the Titan motor. The segment -to-segment case
insulation design results in a compression butt joint which
apparently is often sufficient to withstand Pc, ....
"Your review showed that there was sufficient
margin of O-ring remaining to do the job. I'm sure you have
considered that if it does burn through, the secondary O-ring will
then be similarly pressurized through a single port. So, some concern
remains.
"I recommend that you set up a panel to study
the use of putty and consider some alternatives:
"1) Is putty needed at all?
"2) If the tradition can't be broken, can the
putty be applied with multiple (6 or 8) pressurization paths built
in?
"I think that the primary seal should be
allowed to work in its classical design mode. Both the Titan and STS
Solid Rocket Motors have been designed for this not to happen. Titan
has flown over a thousand pressure joints with no failure. My opinion
is that the potential for failure of the joint is higher for the STS
Solid Rocket Motor, especially when occasionally the secondary seal
may not be totally effective."
75
When the 41-B erosion was taken to the Level I
Flight Readiness Review for 41-C on March 30, 1984, it was briefed as
a"technical issue". A recommendation to fly 41-C was approved by
Level I "accepting the possibility of some O-ring erosion due to the
hot gas impingement."
76
The rationale for acceptance was the same as that
given at the Level III Flight Readiness Review and entered into the
Marshall problem assessment report. An outgrowth of this review was
an April 5, 1984, directive from NASA Deputy Administrator Dr. Hans
Mark to Lawrence Mulloy at Marshall. This "Programmatic Action Item"
was signed by Weeks and asked Mulloy to conduct a "formal review of'
the Solid Rocket Motor case-to-case and case-to-nozzle joint sealing
procedures to ensure satisfactory consistent closeouts."
77
This action item had been preceded by a letter written
from NASA Associate Administrator for Space Flight General Abrahamson
to Marshall Center Director Lucas.
78
That letter, sent January 18, 1984, requested that
Marshall develop a plan of action to make improvement in NASA's
ability to design, manufacture and fly Solid Rocket Motors.
Abrahamson pointed out that NASA was flying motors where basic design
and test results were not well understood. The letter addressed the
overall general Solid Rocket Motor design but did not specifically
mention O-ring erosion.
After Mulloy received the April 5, 1984 STS
41-C action item on the O-rings, he had Lawrence Wear for-ward a
letter- to Thiokol which asked for a formal review of' the booster
field joint and nozzle joint sealing procedures. Thiokol was to
identify the cause of the erosion, determine whether it was
acceptable. define necessary changes, and reevaluate the putty then
in use. The Wear letter also requested small motor tests reflecting
joint dynamics as well as analysis of the booster assembly
process.
79
Thiokol replied to the Marshall STS 41-C
action item on May 4, 1984, with a program plan entitled "Protection
of' SRM Primary Motor Seals." The plan was prepared by Brian Russell,
then Thiokol's Manager of Systems Engineering. It outlined a
systematic program to isolate the 0-ring erosion and charring problem
and to eliminate damage to the joint seals.
80
Proposed areas of inquiry included the leak check
pressures, assembly loads, case eccentricity and putty layup. The
Thiokol response in May 1984 was merely a proposal. The actual final
response to the directive from Marshall was not completed until the
August 19, 1985 briefing on the Solid Rocket Motor seal held at NASA
headquarters some 15 months later.
81
133
Figure 3. Graphs depict flight anomaly
frequency for both field and nozzle joint of solid motors for a
variety of leak check pressures.
Leak Check and Putty
In addition to the action item from NASA
Headquarters, another result of the 41-B erosion was a warning
written by John Q. Miller, Marshall chief of the solid motor branch,
to George Hardy, through Keith Coates.
82
Miller was worried about the two charred rings on 41-B
and the "missing putty" found when the Solid Rocket Boosters were
recovered and disassembled. He specifically identified the putty's
sensitivity to humidity and temperature as potential sources of
problems. "The thermal design of the [Solid Rocket Motor] joints
depends on thermal protection of the O-ring by the [putty]," Miller
said. Failure of the putty to "provide a thermal barrier can lead to
burning both O-rings and subsequent catastrophic failure." The
memorandum also said that "the O-ring leak check procedure and its
potential effect on the (putty) installation and possible
displacement is also an urgent concern which requires expedition of
previously identified full scale tests."
From the beginning, Thiokol had suspected the
putty was a contributing factor in O-ring erosion, even after
STS-2.
83
In April 1983, Thiokol reported on tests conducted to
study the behavior of the joint putty. One conclusion of the report
was that the STS-2 erosion was probably caused by blow holes in the
putty, which allowed a jet of hot gas to focus on a point on the
primary O-ring. Thiokol discovered the focused jet ate away or
"impinged" on portions of the O-ring. Thiokol calculated that the
maximum possible impingement erosion was .090 inch, and that lab test
proved that an O-ring would seal at 3,000 psi when erosion of .095
inches was simulated. This "safety margin" was the basis for
approving Shuttle flights while accepting the possibility of O-ring
erosion.
84
Shortly after Miller's routing slip to Hardy
about the "urgent concern" of the missing putty on 41-B, at Thiokol,
Brian Russell authored a letter to Robert Ebeling which analyzed the
erosion history and the test data. Russell's April 9, 1984 conclusion
was that the putty itself and its layup were not at fault but that
the higher stabilization pressure adopted in leak check procedures,
first implemented in one field joint on STS-9, may increase the
chances of O-ring erosion. The conclusion by Miller and Russell was
that the air pressure forced through the joint during the O-ring leak
check was creating more putty blow holes, allowing more focused jets
on the primary O-ring, thereby increasing the frequency of
erosion.
85
This hypothesis that O-ring erosion is related
to putty blow holes is substantiated by the leak check history
Figure 3
). Prior to January, 1984, and STS 41-B, when the leak
check pressure was [
134
] 50 or 100 psi, only one field joint O-ring anomaly
had been found during the first nine flights. However, when the leak
check stabilization pressure was officially boosted to 200 psi for
STS 41-B, over half the Shuttle missions experienced field joint
O-ring blow-by or erosion of some kind.
86
Moreover, the nozzle O-ring history of
problems is similar. The nozzle joint leak check was changed from 50
psi to 100 psi before STS-9 launched in November 1983. After this
change, the incidence of O-ring anomalies in the nozzle joint
increased from 12 percent to 56 percent of all Shuttle flights. The
nozzle pressure was increased to 200 psi for mission 51-D in April,
1985, and 51-G in June, 1985, and all subsequent missions. Following
the implementation of the 200 psi check on the nozzle, 88 percent of
all flights experienced erosion or blow-by.
87
Both Thiokol and NASA witnesses agreed that
they were aware that the increase in blow holes in the putty could
contribute to O-ring erosion. The Commission testimony of May 2,
1986, reads:
Dr. Walker
: The analysis that some of our staff has done suggests
that after you increase the test pressure to 200 pounds, the
incidence of blow-by and erosion actually increased.
Mr. Russell
We realized that.
Lawrence Mulloy was also questioned above the
blow holes in the putty:
Dr. Walker
: Do you agree that the primary cause of the erosion is
the blow holes in the putty?
Mr. Mulloy
I believe it is. Yes.
Dr. Walker
And so your leak check procedure created blow holes in the
putty?
Mr. Mulloy
That is one cause of blow holes in the putty.
Dr. Walker
But in other words, your leak check procedure could indeed cause what
was your primary problem. Didn't that concern you?
Mr. Mulloy
Yes, sir.
88
Notwithstanding the knowledge that putty blow
holes caused erosion and that higher pressure in the leak check
caused more blow holes, Thiokol recommended and NASA accepted the
increased pressure to ensure that the joint actually passed the
integrity tests.
89
The documentary evidence produced by NASA and
Thiokol demonstrates that Marshall was very concerned about the putty
erosion/blow hole problem after STS 41-B. In addition to John
Miller's routing slip about putty on STS 41-B discussed above, there
is a report of a June 7, 1984, telephone conference between Messrs.
Thompson, Coates and Ray (Marshall) and Messrs. Sayer, Boisjoly,
Russell and Parker (Thiokol), among others.
90
Marshall told Thiokol that NASA was very concerned
about the O-ring erosion problem and that design changes were
necessary, including possible putty changes. The Thiokol engineers
discussed Marshall's suggestions after the telephone conference, but
decided they could not agree a change was mandatory. A follow-up
telephone conference was held between Ben Powers of Marshall and
Lawrence Sayer of Thiokol on July 2. Powers told Saver that NASA
would not accept the removal of the putty from the joint and that
everyone expected the tests to show that gas jets would damage an
O-ring. However, Powers expressly stated that Marshall would not
accept Thiokol's opinion that no further tests were necessary.
In mid-1984, the early tests after NASA's
action item for 41-C led Thiokol to the conclusion that O-ring
erosion was a function of the putty blow hole size and the amount of
free volume between the putty orifice and the O-ring. The damage to
the O-ring was judged to be worse when the blow hole was smaller and
the free volume was larger.
91
While Thiokol did establish plans for putty
tests to determine how it was affected by the leak check in response
to the 41-C action item, their progress in completing the tests was
slow. The action item was supposed to be completed by May 30, 1984,
but as late as March 6, 1985, there are Marshall internal memos that
complain that Thiokol had not taken any action on Marshall's December
1983 directive to provide data on putty behavior as affected by the
joint leak check stabilization pressure.
92
STS 51-C and Cold Temperature
On January 24, 1985, STS 51-C was launched.
The temperature of the O-rings at launch was 53....
135
] Figure 4.
NASA Official
Position
Description of Awareness of O-Ring
Problems
John Young
Chief, Astronaut Office
"The secret seal, which no one that
we know knew about."
93
Milton Silveira
Chief Engineer
". . .If I had known . . . I'm sure
in the '82 time period when we first came to that conclusion
[that the seal was not redundant], I would have insisted
that we get busy right now on a design change and also look
for any temporary fix we could do to improve the operation
of the seal. "
94
James Beggs
(Former) NASA Administrator
"I had no specific concerns with the
joint, the O-rings or the putty...."
95
Arnold Aldrich
Manager, National Space
Transportation System
None were aware of Thiokol's concern
about negative effect of cold temperature on O-ring
performance, nor were they informed of the same concern
raised after STS 51-C.
96
Jesse Moore
(Former) Associate Administrator for
Space Flight
Richard Smith
Director, Kennedy Space Center
James A. Thomas
Deputy Director, Kennedy Launch and
Landing Operations
....degrees, the coldest to that date. O-ring
erosion occurred in both solid boosters. The right and left nozzle
joint showed evidence of blow-by between the primary and secondary
O-rings. The primary O-ring in the left booster's forward field joint
was eroded and had blow-by, or soot behind the
ring.
97
The right booster's damage was in the center field
joint-the first time that field joint seal was damaged. Both its
primary and secondary O-rings were affected by heat, and the primary
ring also had evidence of blow-by of soot behind it. This was also
the first flight where a secondary O-ring showed the effect of
heat.
STS 51-C was the second example of O-ring
damage in flight where there was evidence of blow-by erosion as well
as impingement erosion. As noted previously, impingement erosion
occurs where the O-ring has already sealed and a focused jet of hot
gas strikes the surface of the ring and removes a portion of it.
Blow-by erosion happens when the O-ring has not yet sealed the joint
gap and the edge of the ring erodes as the hot gas flows around
it.
Roger Boisjoly described the blow-by erosion
seen in 51-C:
"SRM 15 [STS 51-C] actually
increased [our] concern because that was the first time we had
actually penetrated a primary,, O-ring on a field joint with hot gas,
and we had a witness of that event because the grease between the
O-rings was blackened just like coal . . . and that was so much more
significant than had ever been seen before on any blow-by on any
joint . . . the fact was that now you introduced another phenomenon.
You have impingement erosion and bypass erosion, and the O-ring
material gets removed from the cross section of the O-ring much, much
faster when you have bypass erosion or blow-by."
98
136
] Boisjoly also said
blow-by erosion was where the primary O-ring "at the beginning of the
transient cycle . . . is still being attacked by hot gas, and it is
eroding at the same time it is trying to seal, and it is a race
between, will it erode more than the time allowed to have it seal."
He described the blow-by on 51-C as "over 100 degrees of arc, and the
blow-by was absolutely jet black. It was totally intermixed in a
homogeneous mixture in the grease." When the blow-by material was
chemically analyzed, Boisjoly said, "we found the products of putty
in it, we found the products of O-ring in it."
99
On the Marshall problem assessment report that
was started to track field joint erosion after STS 41-B, the STS 51
-C O-ring anomaly was described as "O-ring burns were as bad or worse
than previously experienced . . . Design changes are pending test
results."
100
The changes being considered included modifying the
O-rings and adding grease around the O-rings to fill the void left by
putty blow holes.
On January 31, 1985, Marshall Solid Rocket
Booster Project Manager Mulloy sent an urgent message to Lawrence
Wear with the stated subject: "51-C O-Ring Erosion Re: 51-E FRR." The
message ordered that the Flight Readiness Review for the upcoming
flight:
"Should recap all incidents of
O-ring erosion, whether nozzle or case joint, and all incidents where
there is evidence of flow past the primary O-ring. Also, the
rationale used for accepting the condition on the nozzle O-ring.
Also, the most probable scenario and limiting mechanism for flow past
the primary on the 51 -C case joints. If [Thiokol] does not have all
this for today I would like to see the logic on a chart with blanks
[to be filled in ] . "
101
On February 8, 1985, Thiokol presented its
most detailed analysis to date of the erosion problems to the Solid
Rocket Motor project office at Marshall for what was then called
Shuttle mission 51-E, but later changed to 51-D. Thiokol included a
report on damage incurred by the O-rings during flight 51-C at the
left forward and right center field joints. The right center joint
had hot gas past the primary O-ring. Thiokol said that caused a
concern that the gas seal could be lost, but its resolution was
"accept risk."
102
Thiokol presented test results showing
"maximum expected erosion" and "maximum erosion experienced" for both
primary and secondary O-rings for- the field and nozzle joints.
Accepting damage to the primary O-ring was being justified, in part,
based on an assumption of the secondary O-ring working even with
erosion. However, the Criticality classification indicated the
primary seal was a "single point failure." During this flight
readiness assessment at Marshall, for the first time Thiokol
mentioned temperature as a factor in O-ring erosion and blow-by.
Thiokol said in its conclusions that "low temperature enhanced
probability of blow-by-[flight] 51 -C experienced worst case
temperature change in Florida history." Thiokol concluded that while
the next Shuttle flight "could exhibit same behavior," nonetheless
"the condition is not desirable but is acceptable."
103
At the Level I Flight Readiness Review
conducted on February 21, there was no detailed analysis of O-ring
problems presented or any reference made to low temperature effects.
Instead, a single reference indicated the O-ring erosion and blow-by
experienced was "acceptable" because of 'limited exposure time and
redundancy."
STS 51-B and the Launch
Constraint
Joint seal problems occurred in each of the
next four Shuttle flights. Flight 51-D, launched April 12, 1985 had
nozzle O-ring erosion and blow-by on an igniter joint. STS 51-B,
launched 17 days later, experienced both nozzle O-ring erosion and
blow-by as did 51-G, which flew on the following June 17. STS 51-F,
launched duly 29, 1985 had nozzle O-ring blow-by.
104
In response to the apparent negative effect of
cold leading to the extensive O-ring problems on flight 51 -C in
January, Thiokol conducted some O-ring resiliency tests in early
1985.
105
The tests were conducted to quantify the seal timing
function of the secondary O-ring and the effect of joint rotation on
its ability to back up the primary ring. The key variable was
temperature. The June 3 test report, which was described in an August
9, 1985 letter from Brian Russell at Thiokol to Jim Thomas at
Marshall, showed:
"Bench test data indicates that
the O-ring resiliency (its capability to follow the metal) is a
function of temperature and rate of case expansion. [Thiokol]
measured the force of the O-ring against Instron platens, which
137
simulated the nominal squeeze on the O-ring and approximated the case
expansion distance and rate.
"At 100°F, the O-ring maintained contact.
At 75°F the O-ring lost contact for 2.4 seconds. At 50°F,
the O-ring did not reestablish contact in ten minutes at which time
the test was terminated."
106
On June 25, 1985, the left nozzle joint of STS
51-B (launched April 29) was disassembled and inspected after it had
been shipped back to Thiokol. What Thiokol found was alarming. The
primary O-ring seal had been compromised because it eroded .171
inches and it did not seal. The secondary O-ring did seal, but it had
eroded .032 inches. Lawrence Mulloy described the 51-B problem as
follows:
"This erosion of a secondary
O-ring was a new and significant event . . . that we certainly did
not understand. Everything up to that point had been the primary
O-ring, even though it had experienced some erosion does seal. What
we had evidence of was that here was a case where the primary O-ring
was violated and the secondary O-ring was eroded, and that was
considered to be a more serious observation than previously observed
. . .
107
"What we saw [in 51-B], it was evident that
the primary ring never sealed at all, and we saw erosion all the way
around that O-ring, and that is where the .171 came from, and that
was not in the model that predicated a maximum of .090, the maximum
of .090 is the maximum erosion that can occur if the primary O-ring
seals.
"But in this case, the primary O-ring did not
seal; therefore, you had another volume to fill, and the flow was
longer and it was blow-by and you got more erosion."
108
Upon receiving the report of the 51-B primary
ring failure, Solid Rocket Booster Project Manager Mulloy and the
Marshall Problem Assessment Committee placed a "launch constraint" on
the Shuttle system.
109
A 1980 Marshall letter which references "Assigning
Launch Constraints on Open Problems Submitted to MSFC PAS" defines
launch constraint as:
"All open problems coded
Criticality 1, 1R, 2, or 2R will be considered launch constraints
until resolved (recurrence control established and its implementation
effectivity determined) or sufficient rationale, i.e., different
configuration, etc., exists to conclude that this problem will not
occur- on the flight vehicle during pre-launch, launch, or flight."
110
Lawrence Mulloy told the Commission that the
launch constraint was "put on after we saw the secondary O-ring
erosion on the [51-B] nozzle." "Based on the amount of charring," the
problem report listing the constraint said, "the erosion paths on the
primary O-ring and what is understood about the erosion phenomenon,
it is believed that the primary O-ring [of the joint] never sealed."
111
The constraint applied to STS 51-F and all flights
subsequent, including STS 51-L. Although one Marshall document says
that the constraint applied to all O-ring anomalies,
112
no similar launch constraint was noted on the Marshall
Problem Assessment Report that started tracking the field joint
erosion after STS 41-B. Thiokol officials who testified before the
Commission all claimed they were not aware of the July 1985 launch
constraint;
113
however, Thiokol letters referenced Marshall Record
number A09288, the report that expressly identified the constraint.
114
After the launch constraint was imposed,
Project Manager Mulloy waived it for each Shuttle flight after July
10, 1985. Mr. Mulloy and Mr. Lawrence Wear outlined the procedure in
the following manner:
Chairman Rogers
: To you, what does a constraint mean, then?
Mr. Mulloy
A launch constraint means that we have to address the observations,
sec if we have seen anything on the previous flight that changes our
previous rationale and address that at the Flight Readiness
Review.
Chairman Rogers
: When you say»address it," I always get confused
by the word. Do you mean think about it? Is that what you
mean?
Mr. Mulloy
No, sir. I mean present the data as to whether or not what we have
seen in our most recent observation, which may not be the last
flight, it may be the flight before that, is within our experience
base and whether or not the previous analysis and [
138
] tests that
previously concluded that was an acceptable situation is still valid,
based upon later observations....
The constraint was put on after we saw the
secondary O-ring erosion on the nozzle, I believe.
Chairman Rogers
: Who decided that?
Mr. Mulloy
I decided that, that that would be addressed, until that problem was
resolved, it would be considered a launch constraint, and addressed
at Flight Readiness Reviews to assure that we were staying within our
test experience base....
Chairman Rogers
: Do you have ultimate responsibility for waiving the
launch constraints?
Mr. Mulloy
Yes, sir, I have ultimate responsibility for the launch readiness of
the Solid Rocket Boosters.
Chairman Rogers:
So there was a launch constraint, and you waived
it.
Mr. Mulloy
Yes, sir-, all flights subsequent to.
Dr. Ride
I'm trying to understand how you deal with the launch constraint. How
important do you think a launch constraint is and how unusual is it
in your system?
Mr. Wear
: I
think a launch constraint is a significant event in our system, and
it is one that has to be addressed within the Flight Readiness cycle
because I don't have the authority to not do that. .
Dr. Ride
Why didn't you put a launch constraint on the field joint at the same
time?
Mr. Mulloy
I think at that point, and I will react to that question in real
time, because I haven't really thought about it, but I think the
logic was that we had been observing the field joint, the field and
nozzle joint primary O-ring erosion. This erosion of a secondary
O-ring was a new and significant event, very new and significant even
that we certainly did not understand. Everything up to that point had
been that the primary O-ring, even though it had experienced some
erosion, does seal. What we had evidence of was that here was a case
where the primary O-ring was violated and the secondary O-ring was
eroded, and that was considered to be a more serious observation than
previously observed.
Dr. Ride
Correct me if I am wrong, but weren't you basing most of your
decisions on the field joint on analysis of what was the maximum,
what you believed to be the maximum possible erosion, and you had
that analysis for the field joint and for the nozzle joint. When you
saw the complete erosion of the primary O-ring on the nozzle joint,
that showed you that your analysis on the nozzle joint wasn't any
good, I would think. That would indicate to you that your analysis on
the field joint wasn't very good, either, or at least should be
suspect.
Mr. Mulloy
The conclusion, rightly or wrongly, for the cause of the secondary
O-ring erosion on the nozzle joint, it was concluded from test data
we had that 100 psi pressurization leak check, that the putty could
mask a primary O-ring that was not sealing. The conclusion was-and
that one was done at 100 psi. The conclusion was that in order to get
that type of erosion that we saw on the primary O-ring, that that
O-ring never sealed, and therefore the conclusion was that it never
was capable of sealing. The leak check on subsequent nozzles, all
subsequent nozzles was run at 200 psi, which the test data indicated
would always blow through the putty, and in always blowing through
the putty we were guaranteed that we had a primary O-ring seal that
was capable of sealing, and then we further did, and we already had
that on the field joints at that time.
115
While Mulloy and Wear both testified that the
constraint was still in effect and waived for Challenger's flight,
they told the Commission that there had been two erroneous entries on
the O-ring erosion nozzle problem assessment report stating the
O-ring erosion problem had been resolved or closed.
116
Thiokol had suggested this closure on December 10,
1985 (at Marshall's request according to Brian Russell) but Wear and
Mulloy told the Commission they rejected that recommendation and the
problem was still being addressed in Flight Readiness
Reviews.
117
NASA Levels I and II apparently did not realize
Marshall had assigned a launch constraint within the Problem
Assessment System.
118
This......
139
Figure 5. August 19,1985 Headquarters
Briefing.
General Conclusions
Recommendations
All O-ring erosion has occurred
where gas paths in the vacuum putty are formed
Gas paths in the vacuum putty can
occur during assembly, leak check, or during motor
pressurization
Improved filler materials or
layup configurations which still allow a valid leak check
of the primary O-rings may reduce frequency of O-ring
erosion but will probably not eliminate it or reduce the
severity of erosion
Elimination of vacuum putty in a
tighter joint area will eliminate O-ring erosion if
circumferential flow is not present-if it is present,
some baffle arrangement may be required
Erosion in the nozzle joint is
more severe due to eccentricity; however, the secondary
seal in the nozzle will seal and will not erode
through
The primary O-ring in the field
joint should not erode through but if it leaks due to
erosion or lack of sealing the secondary seal may not
seal the motor
The igniter Gask-O-Seal design is
adequate providing proper quality inspections are made to
eliminate overfill conditions
The lack of a good secondary seal
in the field joint is most critical and ways to reduce
joint rotation should be incorporated as soon as possible
to reduce criticality
The flow conditions in the joint
areas during ignition and motor operation need to be
established through cold flow modeling to eliminate
O-ring erosion
QM-5 static test should be used
to qualify a second source of the only flight certified
joint filler material (asbestos-filled vacuum putty) to
protect the flight program schedule
VLS-1 should use the only flight
certified joint filler material (Randolph asbestos-filled
vacuum putty) in all joints
Additional hot and cold subscale
tests need to be conducted to improve analytical modeling
of O-ring erosion problem and for establishing margins of
safety for eroded O-rings
Analysis of existing data
indicates that it is safe to continue flying existing
design as long as all joints are leak checked with a 200
psig stabilization pressure, are free of contamination in
the seal areas and meet O-ring squeeze
requirements
Efforts need to continue at an
accelerated pace to eliminate SRM seal erosion
......communication failure was contrary to
the requirement, contained in the NASA Problem Reporting and
Corrective Action Requirements System, that launch constraints were
to be taken to Level II.
Escalating Concerns
When the burn through of the primary nozzle
O-ring on the left Solid Rocket Booster of STS 51-B was discovered in
Utah on dune 25, 1985, an engineer from the NASA headquarters Shuttle
Propulsion Group was on the scene. Three days after the 51-B
inspection, a memorandum was written to Michael Weeks, also at
Headquarters, reporting on the primary O-ring burn
through.
119
The memo blamed the problem on the faulty 100 psi leak
check and reminded Weeks that Thiokol had not yet responded to the
O-ring erosion action item sent out after STS 41-B one year
earlier.
Engineers at Thiokol also were increasingly
concerned about the problem. On July 22, 1985, Roger Boisjoly of the
structures section wrote a memorandum predicting NASA might give the
motor contract to a competitor or there might be a flight failure if
Thiokol did not come up with a timely solution.
120
Nine days later (July 31) Boisjoly wrote
another memorandum titled "O-ring Erosion/Potential Failure
Criticality" to R. K. Lund, Thiokol's Vice President of
Engineering:
"The mistakenly accepted position
on the joint problem was to fly without fear of failure and to run a
series of design evaluations which would ultimately lead to a
solution or at least a significant reduction of the erosion problem.
This position is now changed as a result of the [51-B] nozzle joint
erosion which eroded a secondary O-ring with the primary O-ring never
sealing. If the same scenario should occur in a field joint (and it
could), then it is a jump ball whether as to the success or failure
of the joint because the secondary O-ring cannot respond to the
clevis opening rate and may not be capable of pressurization. The
result would be a catastrophe of the highest order-loss of human
life."
Boisjoly recommended setting up a team to
solve the O-ring problem, and concluded by stating:
"It is my honest and very real
fear that if we do not take immediate action to dedicate a team to
solve the problem, with the field joint having the number one
priority, then we stand in jeopardy of losing a flight along with all
the launch pad facilities."
121
140
] In reply to
specific questions from Marshall on August 9, Thiokol's Brian Russell
reported the test data on the dune 3 resiliency tests. As noted
previously, he indicated O-ring resiliency was a function of the
temperature and case expansion. Also, he wrote, Thiokol had no reason
to suspect that the primary O-ring would fail after motor ignition
transient. He said the secondary O-ring would seal within the period
after ignition from 0 to 170 milliseconds.
122
From 170 to 330 milliseconds, the probability of the
sealing of the secondary O-ring was reduced. From 330 to 600
milliseconds, there was only a slight chance the secondary seal would
hold.
On August l9, 1985, Thiokol and Marshall
program managers briefed NASA Headquarters on erosion of the motor
pressure seals.
123
The briefing paper concluded that the O-ring seal was
a critical matter, but it was safe to fly. The briefing was detailed,
identifying all prior instances of field joint, nozzle joint and
igniter O-ring erosion. It recommended an "accelerated pace" to
eliminate seal erosion but concluded with the recommendation that "it
is safe to continue flying existing design as long as all joints are
leak checked with a 200 psig stabilization pressure, are free of
contamination in the seal areas and meet O-ring squeeze
requirements." The briefing conclusions and recommendations appear in
Figure 5
124
Thiokol's Robert Lund, Vice
President-Engineering, noting that "the result of a leak at any of
the joints would be catastrophic," announced the establishment of a
Thiokol O-ring task force on August 20, 1985, to "investigate the
Solid Rocket Motor case and nozzle joints, both materials and
configurations, and recommend both short-term and long-term
solutions."
125
Two days later, A. R. Thompson, Thiokol's
supervisor of structures design, said in a memorandum to S. R. Stein,
project engineer, that the "O-ring seal problem has lately become
acute." Thompson recommended near-term solutions of increasing the
thickness of shims used at the tang and clevis mating, and increasing
the diameter of the O-ring. "Several long-term solutions look good;
but, several years are required to incorporate some of them,"
Thompson wrote. "The simple short-term measures should be taken to
reduce flight risks."
126
During a Commission hearing, Thompson was asked about
the larger diameter O-ring solution:
Dr. Walker
: Why didn't you go to the larger O-ring, then?
Mr. Thompson
: One problem in going to larger O-rings is in field
joints-plant joints, excuse me. In the plant joints, if you put in
the 295 and you take the worst on worst, when the joint is raised to
a temperature of 325 degrees during the curing of the insulation, it
is an overfill condition because of the alpha problems with the case,
and the rubber.
Dr. Walker
There is no reason why a field joint and a plant joint had to have
the same O-ring, is there?
Mr. Thompson
: There were some that were afraid of the QC people,
that were afraid of the confusion that might be developed between two
nearly the same sized O-ring.
127
Thiokol's revised O-ring protection plan,
dated August 30, 1985, indicated that NASA and Thiokol were still not
in agreement on the magnitude of the joint rotation phenomenon. It
said that "presently there are conflicting data from Solid Rocket
Motor case hydrotest and [static tests] concerning the magnitude of
case field joint rotation under motor pressure. A referee test will
be devised, which is mutually acceptable to NASA and Thiokol, to
determine joint opening characteristics."
128
Design Questions Resurface
Also in late August, Thiokol submitted
"Preliminary Solid Rocket Motor Nozzle/Field Joint Seal Concepts" to
NASA, which were "formulated to solve the [Solid Rocket Motor]
sealing problems." The document contained 43 possible design concepts
for field joints and 20 for nozzle joints. The report said Thiokol
"feels the case field joint poses the greatest potential risk in that
its secondary seal may not maintain metal contact throughout motor
operation. The nozzle joint is also of major concern because the
frequency and severity of seal damage experienced has been greater
than any other joint."
In September 1985, Thiokol's plans called for
test-firing a static motor with various O-ring configurations. In a
September 10 presentation to Marshall, Thiokol discussed erosion
predictions, and evaluated primary engineering concerns including
joint deflection and secondary O-ring resiliency. Temperature was not
mentioned.
129
141
] Prior to that
Thiokol presentation, Marshall Science and Engineering Director
Kingsbury had informed Solid Rocket Booster Program Manager
Mulloy:
"I am most anxious to be briefed
on plans for improving the Solid Rocket Motor O-ring seals.
Specifically, I want to review plans which lead to flight
qualifications and the attendant schedules. I have been apprised of
general ongoing activities but these do not appear to carry the
priority which I attach to this situation. I consider the O-ring seal
problem on the Solid Rocket Motor to require priority attention of
both Morton Thiokol/Wasatch and MSFC."
130
Early in October, internal warnings about the
lack of results from the O-ring task force came when Thiokol's
management got two separate memoranda complaining about
administrative delays and lack of cooperation. One memorandum was
written by Roger Boisjoly on October 4, 1985, and it warned Thiokol
management about lack of management support of the O-ring team's
efforts.
131
He said that "even NASA perceives that the team is
being blocked in its engineering efforts to accomplish its task. NASA
is sending an engineering representative to stay with us starting
October 14th. We feel that this is the direct result of their feeling
that we [Thiokol] are not responding quickly enough on the seal
problem."
R. V. Ebeling, manager of Thiokol's Solid
Rocket Motor ignition system, began his October 1, 1985, report to
McDonald with the alarming word "HELP!" Ebeling said the seal task
force was "constantly being delayed by every possible means."
"Marshall Space Flight Center," he said, "is correct in stating that
we do not know how to run a development program." Ebeling
continued:
"The allegiance to the O-ring
investigation task force is very limited to a group of engineers
numbering 8-10. Our assigned people in manufacturing and quality have
the desire, but are encumbered with other significant work. Others in
manufacturing, quality, procurement who are not involved directly,
but whose help we need, are generating plenty of resistance. We are
creating more instructional paper than engineering data. We wish we
could get action by verbal request, but such is not the case. This is
a red flag."
132
Shuttle flight 61-A was launched October 30,
1985. It experienced nozzle O-ring erosion and field joint O-ring
blow-by.
133
These anomalies were not mentioned at the Level I
Flight Readiness Review for flight 61-B. That flight was launched on
November 26, 1985, and sustained nozzle O-ring erosion and blow-by.
134
The following month (December) Thiokol's
problem status report which tracked the field joint erosion anomaly
stated that the O-ring task force had made one hot gas test and
preliminary results indicated the test chamber needed to be
redesigned.
135
Mr. Ebeling of Thiokol became so concerned about the
gravity of the O-ring problem that he told fellow members of the seal
task force that he believed Thiokol should not ship any more motors
until the problem was fixed.
In testimony before the Commission, Ebeling
said:
Mr. Ebeling
: Well, I am a hydraulics engineer by profession, and
O-rings and seals and hydraulics are very sacred, but for the most
part, a hydraulics or pneumatics engineer controls the structure, the
structural design, the structural deformation to make sure that this
neat little part that is so critical is given every thing it needs to
operate. In Solid Rocket Motors I have been there now pushing 25
years. They had a different attitude on O-rings when I came there,
and it is not just Thiokol, it is universal.
Dr. Covert
By universal, you mean the solid rocket industry?
Mr. Ebeling
The entire solid rocket industry. It gets around from one, the
competitors' information eventually gets to me by one track or
another, and mine to them, but my experience on O-rings was and is to
this date that the O-ring is not a mechanism and never should be a
mechanism that sees the heat of the magnitude of our motors, and I
think before I do retire, I'm going to make sure that we discontinue
to fly with round seals which I am against round seals anyway. I
think seals with memories, not pressure-activated, but energized
through mechanical means, and in all cases, keep the heat of our
rocket [
142
] motors away from those seals. Whatever it is, you do
not need chamber pressure to energize a seal.
Dr. Covert
In this regard, then, did you have an increasing concern as you saw
the tendency first to accept thermal distress and then to say, well,
we can model this reasonably and we can accept a little bit of
erosion, and then etc., etc. ? Did this cause you a feeling of if not
distress, then betrayal in terms of your feeling about
O-rings?
Mr. Ebeling
I'm sure sorry you asked that question.
Mr. Covert
I'm sorry I had to.
Mr. Ebeling
To answer your question, yes. In fact, I have been an advocate, I
used to sit in on the O-ring task force and was involved in the seals
since Brian Russell worked directly for me, and I had a certain
allegiance to this type of thing anyway, that I felt that we
shouldn't ship any more rocket motors until we got it fixed.
Dr. Covert
Did you voice this concern?
Mr. Ebeling
Unfortunately, not to the right people.
136
The Closure Issue
On December 6, 1985, Thiokol's Brian Russell
wrote Al McDonald, Thiokol Solid Rocket Motor Project Director,
requesting "closure of the Solid Rocket Motor O-ring erosion critical
problems."
137
He gave 17 reasons for the closure, including test
results, future test plans and the work to date of Thiokol's task
force. Four days later (December 10) McDonald wrote a memorandum to
NASA's Wear asking for closure of the O-ring problem. All O-ring
erosion problems, including the problem containing the July 1985
launch constraint, were among the referenced matters that Thiokol
suggested should be closed. McDonald noted that the O-ring problem
would not be fully resolved for some time, and he enclosed a copy of
Thiokol's August 30 plan for improving the motor
seals.
138
Brian Russell described the problem tracking
process and gave the reason for the closure recommendation during the
following exchange:
Mr. Russell
: We have our reliability engineering department, who
is responsible to complete the monthly problem report, and in
addition to that we have our monthly problem review board telephone
conference with NASA and the contractors, of which we are a part, and
the monthly problem review or the monthly problem report that
reliability prepares, they get the information from engineering or
from the office as necessary to complete their status of what has
happened during that month, whether the problem originated that month
or what has been done to close the problem out, and that is submitted
every month, and I for one do review that before it is submitted to
the Marshall Space Flight Center, and so much of the information that
I would read in these reports would be the same information that we
had given in that monthly problem report or over the telephone on the
teleconference.
Chairman Rogers
: Mr. Russell, when you say close the problem out, what
do you mean by that? How do you close it out normally?
Mr. Russell
Normally, whether it takes engineering analysis or tests or some
corrective action, a closeout to the problem would occur after an
adequate corrective action had been taken to satisfy those on the
problem review board that the problem had indeed been closed out.
That is the way that that happens; for example, we had found a loose
bolt on the recovery one time, and we had to take corrective action
in our procedures and in the engineering to make sure that that
wouldn't happen again, and then to verify that corrective action, and
at that point that problem would be ready to be closed out. It
generally involves a report or at least a mention by the review board
stating what had been done to adequately close it out, and then it is
agreed upon by the parties involved. .
Question
What do you understand a launch constraint to mean?
Mr. Russell
My understanding of a launch constraint is that the launch cannot
proceed without adequately-without everyone's agreement that the
problem is under control.
143
Chairman Rogers
: Under
control meaning what? You just said a moment ago that you would
expect some corrective action to be taken.
Mr. Russell
That is correct, and in this particular case on this 51-B nozzle
O-ring erosion problem there had been some corrective action taken,
and that was included in the presentation made as a special addendum
to the next Flight Readiness Review, and at the time we did agree to
continue to launch, which apparently had lifted the launch
constraint, would be my understanding.
Chairman Rogers
: But really my question is: Did you gentlemen realize
that it was a launch constraint?
Mr. Russell
I would like to answer for myself. I didn't realize that there was a
formal launch constraint on this one, any different than some of the
other erosion and blow-by that we had seen in the past.
Mr. Ebeling
I agree. .
Question
: .
. . Mr. Russell, you wrote a letter, did you not, or a memorandum
indicating that the problem should be closed.
Could you explain to the Commission what you
meant by that?
Mr. Russell
Yes. In our December telephone call on the Problem Review Board-and I
can't remember the date-it was around the 9th or so-there was a
request to close the problems out and particularly the ones that had
been open for a long time, of which this was one, and a long time
meaning six months or more.
There was a request from the Director of
Engineering, as I recall it, that we close these problems out.
Dr. Walker
That was the Director of Engineering at Marshall?
Mr. Russell
Yes, at Marshall Space Flight Center. Now, he wasn't in that call. My
understanding is what they told us and my recollection was that Mr.
Kingsbury would like to see these problems closed out.
Now, the normal method of closing them out is
to implement the corrective action, verify the corrective action, and
then the problem is closed, it comes off the board and is no longer
under active review. .
Chairman Rogers
: What was being done to fix it?
Mr. Russell
Well, we had a task force created of full-time people at Thiokol, of
which I was a member of that task team, and we had done some
engineering tests. We were trying to develop concepts. We had
developed some concepts to block the flow of hot gas against the
O-ring to the point where the O-ring would no longer be damaged in a
new configuration.
And we had run some cold gas tests and some
hot gas motor firing tests and were working toward a solution of the
problem and we had some meetings scheduled with the Marshall Space
Flight Center. We had weekly telephone calls where we statused our
progress and there was a team at Marshall also of engineering people
who were monitoring the things that we were doing to fix the problem
with the goal of implementing a fix in our qualification motor No. 5,
which was scheduled at that time in January, this timeframe being
about the December timeframe of last year.
Chairman Rogers
: Can I interrupt? So you're trying to figure out how
to fix it, right? And you're doing some things to try to help you
figure out how to fix it.
Now, why at that point would you close it out?
Mr. Russell
Because I was asked to do it.
Chairman Rogers
: I see. Well, that explains it.
Mr. Rummel
It explains it, but really doesn't make any sense. On one hand you
close out items that you've been reviewing flight by flight, that
have obviously critical implications, on the basis that after you
close it out, you're going to continue to try to fix it.
So I think what you're really saying is,
you're closing it out because you don't want to be bothered. Somebody
doesn't want to be bothered with flight-by-flight reviews, but you're
going to continue to work on it after it's closed out.
139
144
] Marshall received
the Thiokol letter asking for the closure and an entry was placed on
all Marshall Problem Reports referenced in McDonald's December 10
letter indicating"contractor closure received" on December 18, 1985.
140
On January 23, 1986, another entry was placed on the
same reports indicating the "problem is considered closed."
141
Lawrence Mulloy and Lawrence Wear testified those
entries were "in error." They said:
Mr. Mulloy
: The problem assessment system was put in place to
provide visibility throughout the Shuttle system for the types of
problems that do occur, not just in flight, but also in qualification
tests, and in failure of hardware that is back for refurbishment at a
vendor or whatever. And it is a closed loop tracking system that
lists the anomaly .
Now, the entry that is shown in there that the
problem was closed prior to 51-L is in error. What happened there
was, one of your documents here which we did not discuss is the
letter from Mr. McDonald to Mr. Wear which proposed that this problem
be dropped from the problem assessment system and no longer be
tracked for the reasons stated in Mr. McDonald's letter.
That letter was in the review cycle. The
letter, I believe, was dated 10 December 1985. It came into the
center, it was in the review cycle. After Mr. Wear brought this
letter to my attention, my reaction was, we are not going to drop
this from the problem assessment system because the problem is not
resolved and it has to be dealt with on a flight-by-flight
basis.
Since that was going through the review cycle,
the people who run this problem assessment system erroneously entered
a closure for the problem on the basis of this submittal from
Thiokol. Having done that then for the 51-L review, this did not come
up in the Flight Readiness Review as an open launch constraint, so
you won't find a project signature because the PAS system showed the
problem was closed, and that was an error.
Chairman Rogers
: Who made the error? Do you know?
Mr. Mulloy
The people who do the problem assessment system.
Mr. Wear
Mr. Fletcher, and he reports within our quality organization at the
Flight Readiness Reviews, . . . as I think have been described to you
before. There is one from Thiokol to me, and there is one from my
group to Larry, and then Larry, of course, does one with the Shuttle
project office, and so forth, on up the line. At my review and at
Larry's review, here is a heads up given to the quality
representative at that board for what problems the system has open,
and they cross-check to make sure that we address that problem in the
readiness review.
On this particular occasion, there was no
heads up given because their Problem Assessment System considered
that action closed. That is unfortunate.
142
Project Manager Mulloy was asked during
Commission hearings about the original response to O-ring
erosion:
Mr. Hotz
: Mr. Mulloy, I would like to try to understand this in
somewhat simpler terms than you people are used to using.
Is it correct to state that when you
originally designed this joint and looked at it, that you did not
anticipate erosion of any of the O-ring during flights?
Mr. Mulloy
That is my understanding. I entered this program in November of 1982
and I wasn't there on the original design of the joint, but when I
took over the program there was no O-ring erosion anticipated.
Mr. Hotz
: So
that when you did run into signs of O-ring erosion, this was a bad
sign.
Mr. Mulloy
Yes, sir. .
Mr. Hotz
: So
then you decided to introduce a standard based on the measurement or
the possibility of the limits of O-ring erosion. And as those limits,
as the experience went up, your criteria for, say, flight went up
too.
In other words, when you experienced more than
maximum anticipated O-ring erosion, you waived the flight and said
"Well, it's possible to tolerate that. We still have a margin
left."
Mr. Mulloy
Are you speaking of the case where we did not have a primary
seal.
Mr. Hotz
Yes.
145
Mr. Mulloy
: Yes, sir.
That is correct. .
Mr. Hotz
Then you finally, you're talking about these margins of safety, and I
wonder if you could express in either percentages or actual
measurement terms-you have used the term "wide margin." I wonder if
you could give us a quantitative measurement as to what you consider
a wide margin?
Mr. Mulloy
Yes, sir. Well, as I said we had demonstrated that we could stand 125
thousandths of erosion and still seat. The maximum erosion that we
had seen in the case joint was on STS-2, which was 53 thousandths, so
that is a factor of two and a half .
Dr. Keel
: .
. . I think, Larry, if you go back and look at your Flight Readiness
Reviews, that you were relying on less margins than that.
You were arguing in the Flight Readiness
Reviews where you briefed the problems of primary O-ring erosion that
for the worst case for the field joint also that it would be 90
thousandths.
Mr. Mulloy
That is correct.
Dr. Keel
: At
that point you were pointing out that's okay, because you can seal at
95, not at 125 but at 95. It wasn't until later on during the process
that you determined you could seal at 125.
Mr. Mulloy
That is when we got the hot gas test data.
Dr. Keel
: So
that's a five percent margin, roughly, five and a half.
Mr. Mulloy
On the 90 to 95 on a max predictable, yes.
143
Temperature Effects
The record of the fateful series of NASA and
Thiokol meetings, telephone conferences, notes, and facsimile
transmissions on January 27th, the night before the launch of flight
51 -L, shows that only limited consideration was given to the past
history of O-ring damage in terms of temperature. The managers
compared as a function of temperature the flights for which thermal
distress of O-rings had been observed-not the frequency of occurrence
based on all flights (
Figure 6
). In such a comparison, there is nothing irregular in
the distribution of O-ring "distress" over the spectrum of joint
temperatures at launch between 53 degrees Fahrenheit and 75 degrees
Fahrenheit. When the entire history of flight experience is
considered, including"normal" flights with no erosion or blow-by, the
comparison is substantially different (
Figure 7
).
This comparison of flight history indicates
that only three incidents of O-ring thermal distress occurred out of
twenty flights with O-ring temperatures at 66 degrees Fahrenheit or
above, whereas, all four flights with O-ring temperatures at 63
degrees Fahrenheit or below experienced O-ring thermal
distress.
Consideration of the entire launch temperature
history indicates that the probability of O-ring distress is
increased to almost a certainty if the temperature of the joint is
less than 65.
Flight Readiness Reviews
It is clear that contractor and NASA program
personnel all believed that the O-ring erosion/blow-by anomaly, and
even the launch constraint, were problems that should be addressed in
NASA's Flight Readiness Review process. The Flight Readiness Review
is a multi-tiered review that is designed to create an information
flow from the contractor up through Level III at Marshall, then to
Level II officials from Johnson and Level I at Headquarters. With
regard to the Solid Rocket Booster, the process begins at the element
level and culminates in a coordinated Marshall position at the
subsequent Levels II and I Flight Readiness Review.
144
NASA policy manuals list four objectives of
the Shuttle Projects Flight Readiness Review, an intermediate review
between Level III and Level I, when contractors and Level III program
personnel consider the upcoming launch. The stated objectives
are:
"1.To provide the review team with
sufficient information necessary for them to make an independent
judgment regarding flight readiness.
"2. Review solved problems and previous flight
anomalies and establish confidence in solution rationale.
146
[top] Figure 6. Plot of flights with
incidents of O-ring thermal distress as function of
temperature.
[bottom] Figure 7. Plot of flights
with and without incidents of O-ring thermal distress. NOTE: Thermal
distress defined as O-ring erosion, blow-by, of excessive
heating.
147
] "3. Address all
problems, technical issues, open items and constraints requiring
resolution before flight.
"4. Establish the flight baseline
configuration particularly as it differs from previous missions."
145
The Commission has reviewed the various
documentary presentations made by Thiokol and NASA program people for
Flight Readiness Reviews on all Shuttle flights. The O-ring
presentations in those Flight Readiness Reviews have been summarized
in an Appendix to this report.
The erosion on STS-2 was not considered on any
level of the Flight Readiness Review for STS-3.
146
Similarly the heat effect on STS-6's primary O-ring in
the nozzle was not mentioned on the STS-7 Flight Readiness Review in
1983. However, the rationale for acceptance of the "secondary seal
condition" for the lightweight case first flown on STS-6 contained
the observation that an O-ring sealed during a Thiokol test under
3,000 psi where .125 inches had been cut out of the
O-ring.
147
The inattention to erosion and blow-by anomaly
changed when Thiokol filed a problem report on the field joint
erosion after STS 41-B. The O-ring problems (field and nozzle) on
41-B were briefed as a "technical issue" in the 41-C Flight Readiness
Review. "Probable causes" were defined as:
"Putty blow-through at ignition
causes cavity between putty and primary O-ring to fill during
pressurization. Inability of putty to withstand motor pressure. Air
entrapment in putty during mating. Blow holes in putty during joint
leak test."
Thiokol presented the question at its 41-C
preboard to Marshall, "If primary O-ring allowed a hot gas jet to
pass through, would the secondary O-ring survive impingement?"
148
At the 41 -C Level I Flight Readiness Review, on March
30, 1984, Marshall said the erosion phenomenon was "acceptable" and
that blow holes in the putty were the"most probable cause." The
rationale for the acceptance of the possibility of erosion on STS
41-C was:
"Conservative analysis indicates
max erosion possible:
".090 in. (field joint)
".090 in. (nozzle joint)
"Laboratory test of full scale O-ring/joint
cross section shows capability to sustain joint sealing integrity at
3,000 psi pressure using an O-ring with a simulated .095 in. erosion
depth.
"Recommendation:
"Fly STS 41-C accepting possibility of some
O-ring gas impingement."
149
The next significant treatment of the problem
occurred after the coldest flight, 51-C at 53 degrees in January
1985. In part, Thiokol's extensive analysis for the 51-E Flight
Readiness Review was due to the fact that four joints on 51-C had
problems.
150
Additionally, Mr. Mulloy's specific request for a
recap of the O-ring history undoubtedly prompted a full treatment.
Temperature was highlighted as a concern when Mulloy took Thiokol's
analysis up to the Shuttle Projects Office Flight Readiness Review.
That 18-page briefing concluded with the statement that: "STS 51-C
consistent with erosion data based. Low temperature enhanced
probability of blow-by. STS 51-C experienced worst case temperature
change in Florida history. STS 51-E could exhibit the same behavior.
Condition is acceptable."
151
At the Level I Flight Readiness Review for
51-E on February 21, 1985, the previous 18-page analysis had been
reduced to a one page chart with the resolution: "acceptable risk
because of limited exposure and redundancy (Ref. STS 41-C FRR)".
152
No mention of temperature was found in the Level I
report.
The last major discussion of erosion was at
the Level I Flight Readiness Review for STS 51-F (July 2,
1985).
153
An analysis of the failure of the nozzle primary
O-ring to seal due to erosion on flight STS 51-B (April 29, 1985) was
presented. This serious erosion was attributed to leak check
procedures. An increase in the nozzle leak check to 200 psi was
proposed to be a cure. There was no mention of the fact that .171
inches of erosion on the primary O-ring far exceeded a more recent
analysis model prediction of .070 inches maximum possible erosion.
This was a revision of the former prediction of .090 inches. The
launch constraint activated after STS 51-B was not specifically
listed in the Level I Flight Readiness Review for 51-F. The
Commission has also not found any mention of the duly 1985
constraint, or its waiver for subsequent Shuttle flights, in any
Flight Readiness Review briefing documents.
148
] The Commission's
review of the Marshall and Thiokol documentary presentations at the
various Flight Readiness Reviews revealed several significant trends.
First, O-ring erosion was not considered early in the program when it
first occurred. Second, when the problem grew worse after STS 41-B,
the initial analysis of the problem did not produce much research;
instead, there was an early acceptance of the phenomenon. Third,
because of a belief that in-flight O-ring erosion was "within the
data base" of prior experience, later Flight Readiness Reviews gave a
cursory review and often dismissed the recurring erosion as within
"acceptable" or "allowable" limits. Fourth, both Thiokol and Marshall
continued to rely on the redundancy of the secondary O-ring long
after NASA had officially declared that the seal was a non-redundant
single point failure. Finally, in 1985 when temperature became a
major concern after STS 51-C and when the launch constraint was
applied after 51-B, NASA Levels l and II were not informed of these
developments in the Flight Readiness Review process.
Findings
The genesis of the Challenger accident-the
failure of the joint of the right Solid Rocket Motor-began with
decisions made in the design of the joint and in the failure by both
Thiokol and NASA's Solid Rocket Booster project office to understand
and respond to facts obtained during testing.
The Commission has concluded that neither
Thiokol nor NASA responded adequately to internal warnings about the
faulty seal design. Furthermore, Thiokol and NASA did not make a
timely attempt to develop and verify a new seal after the initial
design was shown to be deficient. . Neither organization developed a
solution to the unexpected occurrences of O-ring erosion and blow-by
even though this problem was experienced frequently during the
Shuttle flight history. Instead, Thiokol and NASA management came to
accept erosion and blow-by as unavoidable and an acceptable flight
risk. Specifically, the Commission has found that:
1.The joint test and certification program was
inadequate. There was no requirement to configure the qualifications
test motor as it would be in flight, and the motors were static
tested in a horizontal position, not in the vertical flight
position.
2. Prior to the accident, neither NASA nor
Thiokol fully understood the mechanism by which the joint sealing
action took place.
3. NASA and Thiokol accepted escalating risk
apparently because they "got away with it last time." As Commissioner
Feynman observed, the decision making was:
"a kind of Russian roulette.
[The Shuttle] flies [with O-ring erosion] and
nothing happens. Then it is suggested, therefore, that the risk is no
longer so high for the next flights. We can lower our standards a
little bit because we got away with it last time.... You got away
with it but it shouldn't be done over and over again like that . "
154
4. NASA's system for tracking anomalies for
Flight Readiness Reviews failed in that, despite a history of
persistent O-ring erosion and blow-by, flight was still permitted. It
failed again in the strange sequence of six consecutive launch
constraint waivers prior to 51-L, permitting it to fly without any
record of a waiver, or even of an explicit constraint. Tracking and
continuing only anomalies that are "outside the data base" of prior
flight allowed major problems to be removed from, and lost by, the
reporting system.
5. The O-ring erosion history presented to
Level I at NASA Headquarters in August 1985 was sufficiently detailed
to require corrective action prior to the next flight.
6. A careful analysis of the flight history of
O-ring performance would have revealed the correlation of O-ring
damage and low temperature. Neither NASA nor Thiokol carried out such
an analysis; consequently, they were unprepared to properly evaluate
the risks of launching the 51-L mission in conditions more extreme
than they had encountered before.
149
References
1. Letter, Dorsey to
Hardy, November 7, 1978.
2. Report, "STS-3
through STS-25 Flight Readiness Reviews to Level III Center
Board," NASA.
3. Ibid.
4. Report, "Selection
of Contractor for Space Shuttle Program SRM," NASA. December 12,
1973; GAO Report B-17367, page 339.
5. Ibid., page
6.
6. Ibid., pages 21 and
22.
7. Ibid., page
18.
8. Ibid., page 7
9. Ibid., page
20
10. Chart, "SRM and
Titan III Clevis Joint Comparison," from Pelham presentation to
Commission Development and Production Subcommittees, March 17,
1986, page 3, PC 73978.
11. Chart,
"Segment/Segment Interface," from Pelham presentation to
Commission Development and Production Subcommittee, March 17,
1986, page 2, PC 73977
12. Report, Thiokol
Space Shuttle Joint Review`" Thiokol, February 25, 1986, PC
021453.
13. Ibid.
14. Ibid.
15. Report,
"Presidential Commission Development and Production Panel,
Response to Panel Question/Special Actions- SRM and Titan III
Clevis Joint Comparison," Thiokol, April 3, 1986, PC
073979.
16. Report, 'Original
Design of Joint Assembly SRB Motor Thiokol," Thiokol, July 13,
1973, PC 009350, and Commission Work Session, Panel on Development
and Production, April 17, 1986, page 18.
17. Report, "1974
Proposal Write Up On Case Design." Thiokol, 1974, page 4. 3-3, PC
010957.
18. Ibid page 4. 3-19,
PC 010973.
19. Commission Work
Session, Development and Production Panel, April 7, 1986, page
118.
20. Commission
Interview Transcript, McIntosh, H., April 2, 1986, page 5.
21. bid.
22. Letter, Brian
Russell to Bob Ebeling, Thiokol, April 9, 1986, PC 091702 and
Commission Hearing Transcript, May 2, 1986, pages
2653-2658.
23. Commission Hearing
Transcript, February 6, 1986, page 30.
24. Report, "Space
Shuttle Case Burst Test Report." Thiokol, December 21, 1977, PC
049551-049648, TWR-11664.
25. Ibid.
26. Report,
"Analytical Evaluation of the Space Shuttle Solid Rocket Motor
Tang/Clevis Joint Behavior," Thiokol, October 6, 1978, TWR-12019;
and Report, "SRM Clevis Joint Leakage Study," NASA, October 21.
1977.
27. Commission Hearing
Transcript, February 25, 1986, page 1435.
28. Commission Hearing
Transcript, May 2, 1986, page 2784.
29. Report, "SRM
Clevis Joint Leakage Study," NASA, October 21, 1977, PC
102337.
30. Letter, Miller to
Eudy, January 9, 1978, PC 009923.
31. Letter, Miller to
Eudy, January 19, 1979, PC 009921.
32. Ibid.
33. Ibid., footnote
31.
34. Commission Hearing
Transcript, May 2, 1986, page 2782.
35. Report, "Visit to
Precision Rubber Products Corporation and Parker Seal Company,"
NASA, February 6, 1979.
36. Ibid.
37. Commission Hearing
Transcript, May 2, 1986, page 2782.
38. Report, "Phase I
Design Certification Review," Thiokol, March 23, 1979,
TWR-12230.
39. Report,
"Analytical Evaluation of the Space Shuttle SRM Tang/Clevis Joint
Behavior," Thiokol. October 17, 1978. PC 102302.
40. Report, "Space
Shuttle Verification/Certification Review Propulsion Committee
Cognizant Engineers 5th Meeting,'' NASA, July 10, 1980, pages
C-7-22.
41. Commission Hearing
Transcript, May 2, 1986. page 2307
42. Report,
Verification/Certification Space Shuttle Program Response to
Assessment, " NASA, September 1980, page 59, PC 094010.
43. Report, "SRM
Program Response." NASA, August 15, 1980. PC 102359.
44. NASA Handbook,
NASA. 52300.4(1D-2). Appendix A, page a-1.
45. Commission
Interview Transcript, A. Aldrich, April 8, 1986, page 13.
46. Memorandum,
Abrahamson to Beggs, December 8, 1981.
47. Ibid.
48. Report. ''Erosion
of SRM Pressure Seals," Thiokol. August 19, 1985, Rev. A (February
10, 1986), page A- 4a.
49. Commission
Interview Transcript, Thomas J.W., April 10, 1986, pages 64-66:
and Reports, Marshall Space Flight Center Problem Assessment
Reports, NASA.
50 Report,
"Post-flight Evaluation of STS-2 SRM Components," Thiokol,
January. 1983, part 1, page 2, TWR 13286.
51. Report, "NASA
Response to Commission Request DP-006." NASA, March 17, 1986, PC
074021.
52. Report, "STS-8,
SRB Pre-Board Flight Readiness Review", Thiokol, July 29,
1983.
53. Report, "Retention
Rationale, SRM Simplex Seal," Thiokol, December 1, 1982, page 4.
and Report, 'Critical Items List." NASA, December 17, 1982.
54. Report. "SRB
Critical Items List," NASA, December 17, 1982.
55. Report, "Retention
Rationale, SRM Simplex Seal," Thiokol. December 1, 1982, page
5.
56. Ibid., page
4.
57. Commission
Interview Transcript, McIntosh. H., April 2, 1986, page 66.
58. Commission Hearing
Transcript, May 2, 1986, page 2729-30.
59. Ibid., footnote
31, page 1.
60. Commission Hearing
Transcript, February 26, 1986, pages 1700- 1701.
61. Commission Hearing
Transcript, February 26, 1986, pages 1514-1516.
62. Report, "Space
Transportation System Level I Change Request-Report, SRB Critical
Items List Requirements," NASA, March 2, 1983, page 1; and Report,
"Space Shuttle Program Requirements Control Board Directive -Level
II- SRB Critical Item List Requirements for SRM Case Joint
Assemblies." NASA, March 2, 1983, page 1.
63 Report, "Space
Shuttle Program Requirements Document Level I," NASA, June 30,
1977, page A-8.
64. Commission Hearing
Transcript, May 2, 1986. pages 2842 -2844.
65. Commission Hearing
Transcript, May 2. 1986, page 2845: and Report, "Space Shuttle
Program Requirements Control Board Directive-Level II, SRB
Critical Item List Requirements for SRM Case Joint Assemblies."
NASA, March 2, 1983, page 1.
66. Commission Hearing
Transcript, May 2, 1986, page 2852
67. Commission
Interview Transcript, A. Aldrich. and R. Kohrs, April 8, 1986,
pages 19-20.
68. Commission
Interview Transcript, L. Weeks, April 7, 1986. page 16.
69. Ibid., footnote
54.
150
70. Report, "MSFC Problem Assessment Report-
O-Ring Erosion in the Case to Nozzle Joint," February 26, 1986,
page 1 of 3; and Commission Interview Transcript, W. Hankins,
April 2, 1986, page 11.
71. Report, "Erosion
of SRM Pressure Seals," Thiokol, February 10, 1986, TWR-15150
Revision A; and Chart, "History of O-Ring Damage in Field Joints"
from Thiokol's presentation on February 25, 1986 to Commission, PC
072076 and PC072077.
72. Report, "Case and
Nozzle Joint Configuration Review," Thiokol, July 2, 1980, pages 2
and 5; and Report, "Erosion of SRM Pressure Seals," Thiolol,
August 19, 1986, pages A-4 and A-6, TWR-15150.
73. Report, "Char
Condition on O-Ring Seal in Forward Field Joint of SRM A57 of
STS-11 Flight Mission 41-B," Thiokol entry of March 12, 1984, page
5, TWR-14283; and Report, "MSFC Problem Assessment System-Segment
Joint Primary O-Ring Charred," NASA, February 17, 1984.
74. Report, "MSFC
Problem Assessment System-Segment Joint Primary O-Ring Charred,"
NASA, entry of March 12, 1984, page 5, TWR-14283.
75. Letter, Morefield
to Mulloy, March 9, 1984.
76. Report, "Flight
Readiness Review- 41C Level I," NASA, March 30, 1984.
77. Hans Mark 41-C
Programmatic Action Item, NASA, March 30, 1984.
78. Letter, Abrahamson
to Lucas, January 18, 1984, PC 008191.
79. Letter, Wear to
Kilminster, April 13, 1984, pages 1 and 2.
80. Report,
"Protection of Space Shuttle SRM Primary Motor Seals," Thiokol,
May 4, 1984, PC 014053.
81. Report, "Erosion
of SRM Pressure Seals Presentation to NASA HQ," Thiokol, August
19, 1985, page 1, and "STS 41-C Action Item Closeout," L. Mulloy,
S. Reinartz, NASA, February 20, 1986.
82. Routing slip,
Miller to Hardy, NASA, February 28, 1984, PC 0266494.
83. Report, "SRM FIeld
Joint Zinc Chromate Vacuum Putty Test Report," Thiokol, April 21,
1983, page 13.
84. Report, "SRM Joint
Putty, O-Ring, and Leak History," Thiokol, April 9, 1984, page 1,
TWR-13484.
85. Ibid.; and Report,
"Erosion of SRM Pressure Seals," Thiokol, TWR-15150, page D-16, PC
002963.
86. Ibid.; and Report,
"SRB SRS 9 Flight Readiness Review," NASA, November 4, 1983, page
35.
87. Report, "Erosion
of Solid Rocket Motor Pressure Seals," Thiokol, August 19, 1985,
TWR-15150, PC 021767.
88. Commission Hearing
Transcript, May 2, 1986, page 2687.
89. Commission Hearing
Transcript, May 2, 1986, page 2621.
90. Memorandum,
B.Russell, Thiokol, June 13, 1984, "Minutes of Telecon with NASA
MSFC on June 7, 1984," page 1, PC 102463.
91. Memorandum,
R.Russell, Thiokol, June 1, 1984, "Vacuum Putty/O-Ring Test
Results," page 1, PC 102460.
92. Memorandum,
J.Miller, March 6, 1985, NASA.
93. Memorandum, Young
to Director, Flight Crew Operations, March 3, 1986.
94. Commission
Interview Transcript, M. Silveira, April 16, 1986, page 30.
95. Commission
Interview Transcript, J.Beggs, May 1, 1986, pages 5-6.
96. Commission Hearing
Transcript, February 27, 1986, page 1899.
97. Report, "Flight
Readiness Review STS 51-E SRM-16," Thiokol, February 12, 1985,
pages 3-1 through 3-17.
98. Commission Hearing
Transcript, February 25, 1986, page 1392.
99. Commission Hearing
Transcript, Febrtuary 14, 1986, page 1202.
100. Report, "Problem
Assessment System Record #A07934," NASA, page 3, PC 037598.
101. Memorandum,
"51-C O-Ring Erosion Re: 51-E FRR," Mulloy to Wear, 03/31/85, PC
102482.
102. Report, "STS
51-E Flight Readiness Review," Thiokol, February 8, 1984,
TWR-14740 Rev. B Section 1, page 4.
103. Ibid., Section
6, page 4.
104. Report, "SRM
Seal Erosion Problems," NASA, March 19, 1986, PC 10235.
105. Report, "O-Ring
Resiliency Testing," Thiokol, June 3, 1985, PC 102509; and
Memorandum, "Actions Pertaining to Field Joint Secondary Seal,"
B.Russel, Thiokol, August 9, 1985, PC 102543.
106. Ibid.
107. Commission
Hearing Transcript, May 2, 1986, page 2591.
108. Commission
Hearing Transcript, May 2, 1986, pages 2606-2607.
109. Commission
Hearing Transcript, May 2, 1986, page 2591.
110. Memorandum,
Lindstrom to Distribution, NASA, September 15, 1980, page
1.
111. Report, "MSFC
Problem Assessment System," February 26, 1986, PC 037710.
112. Report, "SRM
Seal Erosion Problem, Revised," March 19, 1986, PC 037593.
113. Commission
Hearing Transcript, May 2, 1986, page 2735.
114. Letter, McDonald
to Wear, Thiokol, December 10, 1985, PC 49701.
115. Commission
Hearing Transcript, May 2, 1986, excerpt beginning pages 2590
through 2646.
116. Commission
Hearing Transcript, May 2, 1986, page 2589.
117. Commission
Hearing Transcript, May 2, 1986, page 2635.
118. Commission
Hearing Transcript, May 2, 1986, page 2867.
119. Memorandum,
Winterhaler to Weeks, June 28, 1985.
120. Memorandum, R.
Boisjoly, July 22, 1985.
121. Memorandum, R.
Boisjoly, July 31, 1985.
122. Letter, "Actions
Pertaining to SRM Field Joint Secondary Seal," Russell to Thomas,
August 9, 1985.
123. Report, "Erosion
of Solid Rocket Motor Pressure Seal Updated from August 19, 1985-
Revised February 10, 1986," Thiokol, TWR-15150, PC 000769.
124. Ibid.
125. Memorandum, Lund
to Sayer, August 20, 1985.
126. Memorandum, "SRM
Flight Seal Recommendation," Thompson to Stein, August 22,
1985.
127. Commission
Hearing Transcript, February 14, 1986, page 1220.
128. Report, "Program
Plan Improvement of Space Shuttle SRM Motor Seal," Thiokol, August
30, 1985, page 6.
129. Report, "Erosion
of SRM Pressure Seals," Thiokol, September 10, 1985, pages A-1 to
C-5.
130. Letter,
Kingsbury to Mulloy, September 5, 1985.
131. Report,
"Activity Report- Solid Rocket Motor Seal Problem Task Team
Status," Thiokol, October 4, 1985.
132. Memorandum,
Ebeling to McDonald, October 1, 1985, page 1.
133. Ibid., page 2;
and Report, "Erosion of SRM Pressure Seals, Update," February 10,
1986, pages A-4a, A-6a, TWR-1510, PC000760.
134. Report, "Level I
STS 61-C Flight Readiness Review," NASA, December 11, 1985.
135. Ibid., footnote
133; and Report, "Solid Motor Branch Significant Events," NASA,
December 12, 1985.
136. Commission
Hearing Transcript, May 2, 1986, pages 2746-2747.
137. Memorandum,
"Closure of SRM O-Ring Erosion Critical Problems," Russell to
McDonald, December 6, 1985.
138. Letter, McDonald
to Wear, December 10, 1985.
151
139. Commission Hearing Transcript, May 2,
1986, pages 2682-2695
140. Report, "Problem
Assessment System," NASA, entry dated December 18, 1985.
141. Ibid., entry
January 23, 1986.
142. Commission
Hearing Transcript, May 2, 1986. pages 2589-2590.
143. Ibid., pages
2619-2623.
144. Commission
Hearing Transcript, February 11, 1986, pages 65O-653.
145. Report, "Shuttle
Project Flight Readiness Review (Prelaunch Activities Team
Report)," NASA, December 29, 1983, page 75.
146. Reports, "STS-3
Flight Readiness Review for Levels I, II, III and
Contractor."
147. Commission
Hearing Transcript, February 26. 1986, page 1639.
148. Report, "STS-13
Solid (41-C) Rocket Motor Flight Readiness Review," Thiokol, March
2, 1984, page 2, TWR-14231.
149. Report STS 41-C
Flight Readiness Review Solid Rocket Booster," NASA, March 30,
1984, page 39.
150. Report, "O-Ring
Erosion on SRM-15," Thiokol, February 12, 1985, pages 1 through
17.
151. Report, "STS
51-E Flight Readiness Review," Thiokol, February 12, 1985,
TWR-14740 Rev. D., Section 3, page 17.
152. Report, "STS 51-E
Flight Readiness Review, Level 1," NASA, February 21, 1985, page
4.
153. Report, "STS 51-F
Flight Readiness Review, Level 1,'' NASA, July 2, 1985, page
5.
154. Commission
Hearing Transcript, April 3, 1986, page 2469.